Updated June 9, 2025 |
serial number |
specialized |
The name of the device |
The content and quantity of the work |
Technical preparation |
Preparation of supplies |
Preliminary process |
Completion time |
remark |
25 |
Machine-mounted |
funnel |
Funnel vibrator mounting, 8 pcs. (fitter + outfitting) |
|
|
|
2025/5/25 |
Done |
26 |
Machine-mounted |
funnel |
Funnel door assembly and cylinder installation, 4 strips |
|
The cylinder did not arrive |
|
|
3 days after arrival |
27 |
Machine-mounted |
funnel |
Funnel level sensors, 6 pcs |
|
|
|
2025/6/5 |
Done |
28 |
Machine-mounted |
funnel |
sonar radar sensors, 4 pcs |
|
|
The base paint is not finished |
2025/6/11 |
The base is installed, the paint is not finished |
29 |
Machine-mounted |
funnel |
Discharge hopper sensor, 1 pc |
|
|
The base paint is not finished |
2025/6/11 |
|
30 |
Machine-mounted |
funnel |
On-funnel sensor mounting, 12 pcs |
|
The drive roller wheel has not arrived |
Positioning of the sensor base |
|
|
31 |
Machine-mounted |
funnel |
Adjustment door and cylinder mounting, 2 pieces |
|
The rack, cylinder and connecting rod did not arrive in China |
|
|
2 days after arrival |
32 |
Machine-mounted |
funnel |
Belt feeder installation under the hopper, 2 sets |
|
Motors, gearboxes and large sedan cars have not yet arrived in China |
|
|
6 days after arrival |
33 |
Machine-mounted |
funnel |
Two sets of hydraulic power stations were installed |
|
Not in stock |
|
|
|
34 |
Machine-mounted |
funnel |
Water tank installation, 2 pcs |
|
|
|
2025/5/15 |
Done |
35 |
Machine-mounted |
funnel |
High-pressure transfer pump installation, 2 pcs |
|
|
|
2025/5/16 |
Done |
36 |
Machine-mounted |
Belt conveyor |
Belt conveyor roller installation, 757 pcs |
|
|
|
2025/5/16 |
Done |
37 |
Machine-mounted |
Belt conveyor |
Belt drive motor mounting, 7 pcs |
|
The coupling has not arrived |
|
|
The coupling has not arrived |
38 |
Machine-mounted |
Belt conveyor |
Gearbox mounting, 7 pcs |
|
|
Wait for the motor wheels to be installed together |
|
The gearbox has arrived |
39 |
Machine-mounted |
Belt conveyor |
Belt-driven roller mounting, 8 pcs |
|
There are still 5 unarrived drive rollers |
|
|
3 have arrived, and they cannot be installed without a base |
40 |
Machine-mounted |
Belt conveyor |
Conveyor belt installation and bonding, 3 sets |
|
|
and so on to drive the roller wheel installation |
|
7 days after the pulley installation is completed |
41 |
Machine-mounted |
Belt conveyor |
Magnetic separator installation, 1 set |
|
The device has not arrived |
|
|
2 days after arrival |
42 |
Machine-mounted |
Belt conveyor |
Metal detector installation, 1 set |
|
The device has not arrived |
|
|
2 days after arrival |
43 |
Machine-mounted |
Loader |
Upper flange cylinder slewing bearing mounting, 1 set |
|
The original screws have not arrived |
|
2025/6/8 |
Completed, temporarily installed, waiting for the original screws to arrive |
44 |
Machine-mounted |
Loader |
Flange cylinder internal drive motor mounting, 6 pcs |
|
The coupling has not arrived |
|
|
The motor arrived at the goods, and the coupling did not arrive |
45 |
Machine-mounted |
Loader |
Flange cylinder slewing bearing centering |
|
|
After the drive motor is installed |
|
|
46 |
Machine-mounted |
Loader |
Grease pumping station installation, 3 pcs |
|
|
|
2025/5/19 |
Done |
47 |
Machine-mounted |
Loader |
Hydraulic cylinder mounting, 2 pcs |
|
|
|
2025/5/16 |
Done |
48 |
Machine-mounted |
Loader |
The tower body and the outer frame are connected with pins |
|
Not in stock |
|
|
|
49 |
Machine-mounted |
Loader |
Installation of hydraulic pump station above the tower, 1 set |
|
The device has not arrived |
|
|
1 day after arrival |
50 |
Machine-mounted |
Loader |
Belt-driven motors on the tower body, 2 pcs |
|
The device has not arrived |
|
|
7 days after arrival |
51 |
Machine-mounted |
Loader |
Belt drive roller installation on the tower body, 8 pcs |
|
The remaining 3 have not arrived |
|
|
5 have arrived, the base has been changed, and the base of the equipment has not yet arrived |
52 |
Machine-mounted |
Loader |
Belt tensioner installation, 1 set |
|
Not in stock |
|
|
2 days after arrival |
53 |
Machine-mounted |
Loader |
Tank chain mounting, 2 sets |
|
Not in stock |
|
|
2 days after arrival |
54 |
Machine-mounted |
Loader |
Discharge chute assembly, 1 set |
|
The cylinder did not arrive |
|
|
2 days after arrival |