Engineering, Procurement & Construction (EPC) for Water Intake and Outfall Technical Requirements
工程、采购和施工 (EPC) 用于取水和排水技术要求

Engineering, Procurement & Construction (EPC) for Water Intake and Outfall of GHAZLAN Expansion 1 IPP PROJECT
GHAZLAN 扩建 1 IPP 项目的取水和排水口工程、采购和施工 (EPC)

Appendix 4
附录 4

Technical Requirements
技术要求

00

FOR BIDDING
用于投标

28-04-2025

REV.

DESCRIPTION

PRE'D

CKD

APPR.

DATE

Contents
内容

Introduction3
引言 3

General Project Description3
一般项目描述 3

Scale of the Project3
项目规模 3

Scope of Document3
文件范围 3

Engineering6
工程 6

General6
常规 6

Design Basis6
设计基础 6

Codes and Standard6
规范和标准 6

Design Life....…………………………………………………………………7
设计生活 ...............................................................................7

Natural Conditions7
自然条件 7

Design options and Results13
设计选项和结果 13

General Layout13
总体布局 13

Preliminary Assessment on Intake and Outfall Locations15
进水口和出水口位置的初步评估 15

Water Intake and Outfall16
进水和出水口 16

Maritime Structure16
海事结构 16

Aids to Navigation19
航海辅助设备 19

Detailed Engineering Plan19
详细工程计划 19

Collect Design Information Associated Site Visit19
收集设计信息 关联的网站访问 19

Numerical Model Studies19
数值模型研究 19

Geotechnical investigation20
岩土工程勘察 20

Survey..……………………………………………………………………20
调查 .................................................................................20

Detailed Design20
详细设计 20

Engineering Organization20
工程组织 20

Engineering Location and Relationship20
工程位置关系 20

Engineering Organization21
工程组织 21

Responsibilities22
职责 22

Engineering Schedule Management24
工程进度管理 24

Engineering Quality Management25
工程质量管理 25

Engineering Quality Management25
工程质量管理 25

Quality Objective and Requirements25
质量目标要求 25

Quality Management Organizational Structure25
质量管理组织结构 25

Quality management process and Control Points27
质量管理过程和控制27

Design Changes28
设计更改 28

Proposed of Design Changes29
设计变更提案 29

Review of DCR29
DCR29 回顾

Revision of Affected Documents29
受影响文件的修订 29

Notification to Affected Parties30
受影响的通知 30

Impact Due to Design Change Notice30
设计变更通知 30 带来的影响

Engineering
工程
Document
公文
Control
控制
30

Document
公文
management
管理
30

Document publication and delivery33
文档发布交付 33

Document filing management33
文档归档管理 33

Confidentiality management33
保密管理 33

Procurement Support33
采购支持 33

Construction Support34
施工支持 34

Procurement36
采购 36

Objective36
目标 36

General36
常规 36

Procurement organization36
采购机构 36

Procurement plan37
采购计划 37

Procurement idea and principle37
采购思路原则 37

Procurement plan37
采购计划 37

Management of package Contractor procurement activities39
包承包商采购活动管理 39

Construction40
建筑 40

General40
一般 40

Construction strategy40
施工策略 40

Construction execution plan40
施工执行计划 40

Project Schedule Narrative41
项目进度叙述 41

Preparation and Arrangement41
筹备安排 41

Document Preparation42
文件准备 42

Site Preparation42
场地准备 42

Personnel Training43
人员培训 43

Mobilization of Staff43
工作人员动员 43

Mobilization of Machinery and Equipment44
机械设备动员 44

Materials Preparation44
材料准备 44

The mainly construction method statement44
主要施工方法陈述 44

Trenching..……………………………………………………………………45
挖沟 ................................................................................45

Bedding and Leveling46
床上用品调平 46

Pipe Installation46
管道安装 46

Backfilling..……………………………………………………………………47
回填 ................................................................................47

Prefabrication and Installation for Water Intake Riser47
立管 47预制和安装

Navigation facilities48
导航设施 48

Health, Safety, Security and Environment plan for worksite48
工作场所健康、安全、安保和环境计划 48

Quality control49
质量控制 49

Pre-commissioning49
预调试 49

Appendix51
附录 51

Appendix 1: Project Organization Chart and Site Construction Management Organization Chart51
附录 1:项目组织结构图和现场施工管理组织51

Appendix 2: Schedule for Water Intake and Outfall of Ras Mohaisen SWRO Independent Water Project51
附录 2:Ras Mohaisen SWRO 独立务项目 51 的取水和排水口时间表

Appendix 3: Drawings List51
附录 3: 图纸清单 51

Introduction
介绍

General Project Description
一般项目描述

GHAZLAN Expansion 1 IPP project is located at 60 km from Dammam and 450km from Riyadh, Saudi Arabia. Site is allocated some 10 km north of Dhahran Jubail Expressway.
GHAZLAN 扩建 1 IPP 项目距离达曼 60 公里,距离沙特阿拉伯利雅得 450 公里。该地块位于 Dhahran Jubail 高速公路以北约 10 公里处。

The power plant will comprise two (2) sets of multi-shaft 4 + 4 + 1 configuration (4 GTs + 4 HRSGs + 1 ST) combined cycle power generation units.
该发电厂将包括两 (2) 套多轴 4 + 4 + 1 配置(4 GT + 4 HRSG + 1 ST)联合循环发电机组。

Hereinafter the bidder part may be referred as CONTRACTOR, and the EPC Lead, CEEC EPC JV of Ghazlan 1 Expansion Project, may be referred as CUSTOMER.
以下投标人部分可称为 CONTRACTOR,EPC 牵头Ghazlan 1 扩建项目的 CEEC EPC JV 可称为 CUSTOMER。

The proposed location of the Project is to be constructed in Saudi Arabia as follows.
该项目的拟议地点将在沙特阿拉伯建设,如下所示。

Figure 1.1-1: Location of the Project
图 1.1-1.. 项目位置

Scale of the Project
项目规模

The design work consists of water intake, brine outfall, chlorination dosing systems for Ghazlan 1 Expansion Project,the seawater intake quantity is about 12000 m3/h,and the brine water drainage quantity is about 7200 m3/h.
设计工作包括加兹兰 1 号扩建项目的取水口、盐水排放口、氯化加药系统,海水取水量约 12000 m3/h,盐水排水量约 7200 m3/h。

The work mainly contents seawater intake channel, intake pond,brine outfall pipelines and outfall diffusers.
主要工作内容包括海水取水通道 进水池、 盐水排放管道和排放扩散器。

Scope of Document
文件范围

This document is defined for the Water Intake and Outfall project (further referred to as “Project”).
本文件针对 取水口和出水口项目(以下简称“项目”) 定义

This document provides the brief project execution plan and method statement for the Project which CONTRACTOR will conduct to complete the project as CUSTOMER.’s requirement such as engineering, procurement and construction.
文件提供了承包商根据客户的要求完成项目 工程、采购)将进行的项目的简要项目执行计划和方法说明和建筑。

The main scope of works for the project:
该项目的主要工作范围

Fabrication of Intake channel,intake pond, and outfall pipelines
制造进水通道、进水池和出水管道

Dredging
疏浚

Pipeline installation, bedding and haunching
管道安装、铺设和腋部

Backfilling
回填

Required testing
所需测试

The Pipeline details:
管道详细信息:

The recommended water intake and outfall layout is proposed to fulfill sufficient relevant water depth for both intake and outfall.
建议的进水和出水口布局旨在满足进水和出水的足够相关水深

Figure 1.3-1 The proposed General Arrangement of the Water Intake and Outfall Layout
图 1.3-1 建议进水口和出水口布局的总体布局

Construction and operation one (1) intake channel, one (1) intake water pond and one (1) outfall pipeline. The length information is as follows(for reference)
建造和运营一 (1) 个进水通道、一 (1) 个进水池和一 (1) 个排污管道。长度信息如下(供参考)
:

Description
描述

Main Quantity
主要数量

Size of intake channel
进气通道尺寸

Length:1000m
长度:1000m

Width:20m
宽度:20m

Size of intake pond
进水的大小

Length:110m
长度:110m

Width:50m
宽度:50m

Maritime length of discharge Line
卸货线海上长度

Length:900m
长度:900m

One DN1200 GRP pipeline
一条 DN1200 GRP 管道

Discharge Diffuser
卸料扩散器

20×DN250

The schedule:
时间表:

Intake and Outfall project shall be in full operation, before NTP + Months
进水口和出水口项目应在 NTP + 月份之前全面运行

The design boundary is the outer wall of the Intake pumping station and Outfall chamber (the structure of the Intake pumping station, Outfall chamber and chlorination production system are not in the scope).
设计边界为进水泵站和出水室的外壁 进水站、 出水氯化生产系统的结构不在 范围内)。

Note: If the above information/requirements change in the future, this document will be updated accordingly.
注意:如果上述信息/要求将来发生变化,本文档将进行相应更新。

Engineering
工程

General
常规

Contractor will prepare appropriate design management methods for the Water Intake and Outfall Project, including design schedule management, quality management, change management, document management, service management, and other details content etc., and carries out the relevant design work strictly comply with this management document during the whole process of project execution period.
承建商为取水口及出水口工程准备适当的设计管理办法,包括设计进度管理、质量管理、变更管理、文件管理、服务管理及其他详细内容等,并在项目执行全过程中严格遵守本管理文件进行相关设计工作。

Contractor will be responsible for the design within the defined battery limits. Scope of works for engineering will be carried out by CONTRACTOR within the specification, codes, standards and criteria as stated in this proposal and will be performed in line with good engineering practice.
承包商将负责在规定的电池限制内进行设计。工程工作范围承包商根据本提案中规定的规范、 规范、 标准和标准进行,并将按照良好工程实践进行。

Contractor’s Engineering team will be responsible for:
承包商的工程团队将负责:

Engineering Survey & Geotechnical Engineering Investigation Numerical Current & Sediment & Wave Model Study
工程勘测和岩土工程调查数值电流和沉积物和波浪模型研究

Detailed Engineering Design Procurement Support Construction Support
详细的 工程设计 采购支持 施工支持

Design Basis
设计基础

Codes and Standard
代码和标准

The design standards, criteria, parameters and requirements as required for the design of engineering works will be in accordance with the project specifications and requirements as set out in relevant specifications of the Contract Documents.
工程设计所需的设计标准、准则、参数及要求,将按照合同文件相关规格所载的项目规格及要求进行。

Dredging
疏浚

BS 6349-5-2016 Code of practice for dredging and land reclamation
BS 6349-5-2016 疏浚和土地复垦作规范

Maritime structures
海事结构

API Recommended Practice 2A-WSD, 21st edition Planning, Designing, and Construction Fixed Offshore Platforms-Working Stress Design
API 推荐实践 2A-WSD,第 21 版规划、设计和施工固定海上平台 - 工作应力设计

API RP 2GEO –Geotechnical and Foundation Design Considerations
API RP 2GEO – 岩土工程和基础设计注意事项

API Spec 5L Specification for Line Pipe
API Spec 5L 管线规范

AWS D1.1 Structural Welding Code
AWS D1.1 结构焊接规范

BS 6349 Parts 1-8 Code of Practice for Maritime Structures
BS 6349 第 1-8 部分 海事结构作规范

BS 8004 Code of practice for foundation
BS 8004 基础实践守则

BS EN ISO 12944 Paints and varnishes – Corrosion protection of steel structures by protective paint systems
BS EN ISO 12944 油漆和清漆 - 保护漆系统对钢结构的防腐保护

BS 4449 Hot-rolled steel bars for reinforcement of concrete
BS 4449 混凝土加固用热轧钢筋

BS EN 1990 Basis of Structures
BS EN 1990 结构基础

BS EN 1991 Actions on structures
BS EN 1991 对结构的作用

BS EN 1992 Design of Concrete Structures
BS EN 1992 混凝土结构设计

BS EN 1997 Geotechnical Design
BS EN 1997 岩土工程设计

BS EN 1998 Design of Structures for Earthquake Resistance
BS EN 1998 抗震结构设计

CIRIA C683 The Rock Manual - The use of rock in hydraulic engineering (2nd edition)
CIRIA C683 岩石手册 - 岩石在水利工程中的应用(第 2 版)

UBC 1997 Uniform Building Code
UBC 1997 统一建筑规范

Water Intake and drainage
进水和排水

National Standard Plumbing Code
国家标准水暖规范

Uniform Plumbing Code
统一管道规范

American Water Works Association
美国自来水工程协会

American Society for Testing & Materials
美国材料与试验协会

International Standards Organization;
国际标准组织;

AWWA M45 Fiberglass pipe design
AWWA M45 玻璃纤维管设计

AWWA C950 Fiberglass pressure pipe
AWWA C950 玻璃纤维压力

BS EN 752 Drain and sewer systems outside buildings
BS EN 752 建筑物外的排水和下水道系统

PD 8010 Code of practice for pipelines-Part 2: Subsea pipelines
PD 8010 管道作规范 - 第 2 部分:海底管道

Aids to Navigation
导航辅助设备

Marine Aids to Navigation Manual (NAVIGUIDE 2018,8th, Edition, IALA)
船用导航辅助设备手册 (NAVIGUIDE 2018,第 8 版,IALA)

Marine Signal Lights (IALA Recommendation E-200)
船用信号灯(IALA 建议 E-200)

Maintenance of Aids to Navigation (IALA Guideline No.1077)
助航设备维护 (IALA 指南第 1077 号)

Design Life
设计寿命

Design life for the structures, shall be at least:
结构的设计寿命,应至少为:

40 years for civil works and buried pipelines;
土木工程和埋地管道 40 年 ;

10 years for buoys, and the equipment (including navigation lights, solar power system and auxiliaries) for a maintenance-free design life of 5 years.
浮标 10 设备 (包括导航灯、 太阳能发电系统和辅助设备)免维护设计寿命 5 年。

Natural Conditions
自然条件

1)Climatic conditions
1) 气候条件

Climatic conditions to be considered for the design and rating of the Project are shown in the following Table 2.2.3-1.
项目设计和评级应考虑的气候条件如下表 2.2.3-1 所示

Table 2.2.3-1:Design climatic conditions
2.2.3-1 设计气候条件

Item
项目

Unit
单位

Value
价值

Ambient pressure:
环境压力:

Mean ambient pressure
平均环境压力

mbar
毫巴

1013

Ambient Air temperature
环境空气温度

Maximum recorded
记录的最大数量

°C

48

Mean daily maximum (hottest month)
平均每日最大值(最热月份)

°C

41

Annual mean
年平均值

°C

29

Minimum recorded
记录的最小值

°C

5

Rainfall
雨量

Annual average
年平均

mm
毫米

60

Maximum recorded rainfall in one day
单日最大记录降雨量

mm
毫米

50

Maximum rainfall intensity for one hour
一小时的最大降雨强度

mm
毫米

50

Design wind speed and direction [to be confirmed]
设计风速和风向 [待确认]

Basic Wind Speed,(Serviceability design), 3-sec.gust MRI=50.yr
基本风速,(正常使用设计 ),3 秒阵风 MRI=50.yr

m/s
米/

38

Basic Wind Speed,(Ultimate Limit State), 3-sec.gust MRI=1700.yr
基本风速,( 极限状态), 3 秒阵风 MRI=1700.yr

m/s
米/

50

Exposure Category (see Note 1 of SAES-A-112)
暴露类别(参见 SAES-A-112 的注 1)

C

Prevailing wind direction
盛行风向

NNW

Dust
灰尘

Dust concentration in the air [to be confirmed]
空气中的粉尘浓度 [待确认]

mg/m³
毫克/立方米

1.0 – 2.0

Dust concentration in the air under sandstorm condition [tbc]
沙尘暴条件下空气中的粉尘浓度 [待定]

g/m³
克/立方米

Approx. 100
约 100

Maximum relative humidity (recorded at 40°C)
最大相对湿度(在 40°C 时记录)

%

65

Minimum relative humidity
最小相对湿度

%

20

Yearly average relative humidity
年平均相对湿度

%

44

Annual mean Thunder storm day
年平均雷暴日

day

20

Conditions of Gas at Fuel Delivery Point (for design of systems and facilities)
燃料输送点的气体条件(用于系统和设施的设计)

--

See Attachment 06A
见附件 06A

The evaporation pond shall be in line with the hundred years return frequency maximum rainfall scenario.
蒸发池应符合百年一遇的回程最大降雨量情景。

The wind rose is as below:
风向图如下:

2)Reference Site Conditions
2)参考现场条件

Reference Site Conditions (“RSC”) for the design and performance of the Plant are shown in the following Table 2.2.3-2.
工厂设计和性能的参考场地条件 (“RSC”) 如下表 2.2.3-2 所示。

Table 2.2.3-2:Reference Site Condition (RSC)
2.2.3-2 参考站点条件 (RSC)

Item
项目

Unit
单位

Value
价值

Reference Site Conditions (RSC)
参考站点条件 (RSC)

Ambient air temperature
环境空气温度

°C

46

Relative humidity
相对湿度

%

40

Ambient air pressure
环境气压

mbar
毫巴

1013

Transmission System frequency
传输系统频率

Hz
赫兹

60

Sea water temperature
海水温度

°C

32

Water Level (for reference)
(供参考)

Tides
潮汐

The relevant tidal characteristic levels are summarized in table below.
下表总结了相关的潮汐特征水平。

Table 2.2.3-4: Tidal levels
表 2.2.3-4:潮汐水位

Description
描述

Abbreviation
缩写

Datum (m MSL)
基准面 (m MSL

Datum (m LAT)
基准 (m LAT

Highest Astronomical Tide
最高天文潮

HAT

+1.07

+2.16

Mean High Water Spring
Mean High Water 泉

MHWS

+0.84

+1.21

Mean Higher High Water
平均更高的高水位

MHHW

+0.66

+1.75

Mean Lower High Water
平均 Lower High Water

MLHW

+0.42

+1.51

Mean Sea Level
平均海平面

MSL

+0.00
+0.00

+1.09

Mean Higher Low Water
平均 Higher Low Water

MHWL

-0.37

+0.72

Mean Lower Low Water
平均 Lower Low Water

MLLW

-0.68

+0.41

Mean Lower Water Spring
平均下水泉

MLWS

-0.88

+0.21

Lowest Astronomical Tide
最低天文潮

LAT

-1.09

+0.00
+0.00

Operational high water level = MHWS = +0.84 mMSL
运行高水位 = MHWS = +0.84 mMSL

Operational low water level = MLWS = -0.88 mMSL
运行低水位 = MLWS = -0.88 mMSL

Design water level
设计水

The 50-year return periods high water level is considered to be MHWS plus sea level rise plus 50-year return periods storm surge: 0.84 +0.30+ 0.50 = +1.64 mMSL
50 年重现期的高水位被认为是 MHWS 加上海平面上升加上 50 年重现期风暴潮:0.84 +0.30+ 0.50 = +1.64 mMSL

The 50-year return periods low water level is considered to be MLLW plus 50-year return periods negative storm surge: -0.88– 0.73 = -1.61 mMSL.
50 年重现期的低水位被认为是 MLLW 加上 50 年重现期的负风暴潮:-0.88– 0.73 = -1.61 mMSL。

The 100-year return periods high water level is considered to be MHWS plus sea level rise plus 100-year return periods storm surge: 0.84 + 0.30 + 0.59 = +1.73 mMSL.
100 年重现期的高水位被认为是 MHWS 加上海平面上升加上 100 年重现期风暴潮:0.84+ 0.30 + 0.59 = +1.73 mMSL。

The 50-year return periods low water level is considered to be MLLW plus 100-year return periods negative storm surge: -0.88– 0.83 = -1.71 mMSL.
50 年重现期的低水位被认为是 MLLW 加上 100 年重现期的负风暴潮:-0.88– 0.83 = -1.71 mMSL。

Wave Condition
WaveCondition (波形条件)

In order to understand the nearshore wave characteristics of the project sea area, the wave measurement has been conducted from March 03, 2025 to April 04, 2025, with -5.3 m water depth.
为了解项目海域的 近岸波浪特征,于 3 月 3 日、2025 日至 44 日、2025 日进行了波浪 测量 为 -5.3 m。

The maximum significant wave height is 1.5m with the peak wave period of 5.6s. At 67.45% of the observation time, the significant wave height is less than 0.5m, while the maximum significant wave height rarely exceeds 1.0 m (6.43% of the observation time). Meantime, wave periods increase with the growth of wave height, and 96.46% of wave periods are less than 8 s.
最大有效波高为 1.5m,峰值波周期为 5.6s。 67.45% 的观测时间下,有效波高小于 0.5 m,而最大有效波高很少超过 1.0 m( 观测时间的 6.43%) 。同时,波周期随着波高的增长而增加,96.46% 的波周期小于 8 s。

Fig. 2.2.3-5: Wind rose (March-April 2025)
图 2.2.3-5: 风向 3 月至 4 月 20 日 25

Current
当前

In order to understand the nearshore tidal current characteristics of the project sea area, the tidal current measurement has been conducted from March 03, 2025 to April 04, 2025. Two tidal current stations of P1(with water depth of -5m) and P2(with water depth of -9m) has been built
为了解项目海域的近岸潮汐流特征,已于 2025 年 3 月 3 日至 2025 年 4 月 4 日进行了潮汐流测量。已建成 P1(水深-5m)和 P2(水深-9m)两个潮汐站
.

For station P1, the maximum current velocities range from 0.17m/s to 0.25 m/s across different layers, while the average current velocity is between 0.05 m/s and 0.06 m/s within each individual layer.
对于站点 P1,最大电流速度范围为 0。17m/s 降至 0。 25 m/s,而平均电流速度在 0.05 m/s 和 0. 每层内为 06 m/s。

For station P2, the maximum current velocities range from 0.28m/s to 0.38 m/s across different layers, while the average current velocity is between 0.11 m/s and 0.13 m/s within each individual layer.
对于 P2 站,不同层的最大电流速度范围为 0.28m/s 至 0.38 m/s,而每层内的平均电流速度在 0.11 m/s 至 0.13 m/s 之间。

Geological condition (for reference)
地质条件 (供参考)

The soil stratum on the project site is mainly comprised of:
项目现场的土层主要包括:

Silty sand, loose to very loose, brown to dark gray, damp to wet.
粉砂,松散到非常松散,棕色到深灰色,潮湿到潮湿。

Silty clay with sand, medium stiff, dark gray, wet.
粉质粘土带沙子,中等硬度,深灰色, 潮湿。

Silty sand with sea shell and coral fragments, very loose to loose, dark gray to gray, wet.
粉砂质沙子有贝壳和珊瑚碎片,非常松散到松散,深灰色到灰色, 潮湿。

Silty clay with sand, very stiff, dark gray, wet. (BH-1 to BH-6)
粉质粘土带沙子,非常坚硬,深灰色,潮湿。(BH-1 到 BH-6)

Silty coralline sand with coral and sea shell fragments. Very dense, gray to creamy, wet.
粉质珊瑚沙,带有珊瑚和贝壳碎片。非常致密,灰色至奶油状, 潮湿。

Further geotechnical investigation will be confirmed during detail design.
在详细设计期间将确认进一步的岩土工程勘测

Seismic condition (for reference)
地震条件 (供参考)

According to the global seismic hazard map, as shown below. The PGA (50 years’ service with a 10% probability) at project site is estimated in the range of 0.03g - 0.05g.
根据全球地震灾害图,如下图。项目现场的 PGA(50 年服务,概率为 10%)估计在 0.03 克 - 0.05 克之间。

Fig. 2.2.3-5: Global seismic hazard map
图 2.2.3-5: 全球地震灾害图

Design options and Results
设计选项和结果

After review the tender drawings and specification supplied by the OWNER, based on the collection information of meteorological conditions, hydrological condition and geological conditions. The recommended design scheme is as follows.
在审查船东提供的招标图纸和规格书后,根据气象条件、水文条件和地质条件的收集信息。建议的设计方案如下。

The relating drawings please see “Appendix 3: Drawings List”.
有关附图 附录 3:附图清单 ”。

General Layout
总体布局

Coordinates and Elevation Datum
坐标和高程基准面

All horizontal coordinates shall refer to WGS84 system. All levels datum shall be in meters relative to MSL level.
所有水平坐标均应参照 WGS84 系统。所有级别基准面均应以米为单位,相对于 MSL 级别。

Water Intake and Outfall Layout
取水口和出水口布局

The original water intake and outfall layout are based on the existing project information.If the above arrangement changes in the future based on the bathymetric survey, numerical brine plume dispersion modeling study and others, the EPC of this project will be updated accordingly.
原取水口和出水口布局以现有项目信息为基础 ,如果将来根据测深测量、数值盐水羽流扩散建模研究等改变上述安排,本项目的 EPC 将相应更新。

Preliminary Assessment on Intake and Outfall Locations
进水口及出水口位置的初步评估

Based on the CUSTOMER’s Preliminary investigation and research, 900m is estimated to be sufficient for the brine plume to disperse, and the salinity increase at the outfall edge is able to meet the requirements of ESIA and NCEC regulations.
根据客户的初步调查和研究 估计 900m 足以让盐水羽流散去, 排污口边缘的盐度增加能够 满足 ESIA 和 NCEC 法规的要求

Numerical brine plume dispersion modeling study will be carried out in the next phase to study the salinity dispersion and to justify the intake and outfall locations.
下一阶段进行数值水羽流扩散建模研究 ,以研究盐度扩散并证明进水和出水口位置的合理性。

Water Intake and Outfall
取水口和出水口

General
常规

The water intake and water outfall design include:
取水口和出水口设计包括:

Seawater intake system (Seawater Intake channel, seawater intake pond and chlorination pipeline from seawater intake pump station to seawater Intake pond);
海水取水系统(海水取水通道 、海水取水和从海水取水泵站到海水取水池的氯化管道 );

Outfall system (Outfall pipeline from outfall chamber to outfall diffusers).
出水口系统(从出水口室到出水口扩散器的出水管道)。

Water intake system
取水系统

The operation of the intake system concept is to abstract water from the sea into the pump station using gravity at all states of the tide.
进水系统概念的工作原理是在潮汐的所有状态下利用重力将海水从海中抽入泵站。

In this project, the seawater intake total flow rate is about 12000m3/h.
在本项目中,海水取水总流量约为 12000m3/h。

One water intake channel and one water intake pond will be adopted for the water intake system,of which the bottom elevation should be set at approx -3.50m ~-4.00mMSL, to ensure that sufficient water can be obtained at low tide levels
取水系统将采用 1 个取水通道和 1 个取水池,其中底部标高应设置在 -3.50m ~-400mMSL 左右,以确保在低潮位时获得充足的水
.

In order to prevent the breeding of marine organisms in the water intake pond, the chlorination pipes will be arranged at the entrance of water intake pond , and put chlorine to the water intake system. The chlorination pipelines is DN100 HDPE pipe, and the chlorine is supplied from the chlorination station at onshore area, which is not within the scope of work.
防止海洋生物取水池中滋生 ,将在入口处设置加氯管 ,并将氯气通入取水系统。氯化管道为 DN100 HDPE 管,氯气由 陆上地区的加氯供应,不在工作范围内。

To avoid the entry of large organisms, duplex stainless-steel screens will be set at the entrance of water intake pond, with a spacing of 100mm, and avoid sand, silt infiltration and entrainment of smaller organisms, the inflow velocity of the screens shall be not greater than 0.15m/s.
为避免大型生物的进入, 在进入口处设置双相不锈钢滤网 ,间距为 100mm,避免沙子、淤泥渗入和夹带较小生物,滤网的流入速度应不大于 0.15m/s。

Along the pipes, maintenance manholes (minimum diameter 1200 mm) shall be provided at least every 200 m in order to allow inspection and maintenance works by divers.
沿管道至少每 200 米提供维护沙井(最小直径 1200 毫米),以便潜水员进行检查和维护工作。

Water outfall system
出水口系统

The brine outfall system comprises of outfall diffusers structures, brine outfall pipelines and outfall chamber, the outfall chamber is out of the work range.
盐水排放口系统由排放口扩散器结构、盐水排放管道和排放室组成,排放室超出工作范围。

The flow rate of brine outfall pipelines is about 7200 m3/h, one brine outfall pipeline of ID1200 (1x100%) with GRP material will be adopted.
盐水排污管道的流量约为 7200 m3/h,将采用一条 ID 为 1200 (1x100%) 的 GRP 材料盐水排污管道

The flow velocity of the brine outfall pipeline is approx 1.77m/s.
盐水排放管道的流速约为 1。77 米/秒。

20 outfall diffusers will be set at end of the outfall pipeline. The diameter of the outfall diffuser is ID250, and the angle between the diffuser and the horizontal is 45°. Rubber duckbill valve will be set at the end of each diffuser.
20 个出水口扩散器将设置在出水口管道的末端。出风口散流器的直径为 ID250,散流器与水平面之间的夹角为 45°。橡胶鸭嘴阀将设置在每个扩散器的末端。

Maritime Structure
海事结构

Materials
材料

The materials properties should meet the specifications, which are shown in following table.
材料属性应符合下表所示的规格。

Table 2.3.4-1 Properties list
表 2.3.4-1 属性列表

Type of Structure
结构类型

Properties
性能

Pipelines
管道

GRP pipe
GRP 管材

Reinforcement bar
钢筋

Grade B500B or equivalent
等级 B500B 或同等水平

Stainless Steel Structure
不锈钢结构

Duplex stainless steel SS2507
双相不锈钢 SS2507

Concrete
混凝土

C40/50
C40/50 系列

Durability Design
耐久性设计

(1) Corrosion Protection for Concrete
(1) 混凝土的防腐保护

Concrete grade shall be C40/50, concrete cover, strength, cracking widths control, water/cement Ratio, etc. shall be in accordance with relevant codes and standards.
混凝土等级应为 C40/50,混凝土覆盖层、强度、开裂宽度控制、水灰比等应符合相关规范和标准。

Design scheme for Intake channel
进气通道设计方案

Water intake structures include Intake channel and intake pond.
取水结构包括进水通道和进水池。

The water intake channel is a excavation channel with a length of 1000m and a width of 15m.
取水通道为开挖通道,长 1000 m,宽 15 m。

the water intake pond is a rectangular pond with a length of 110m and a width of 50m and the pond is surrounded by stone dam. Set up reinforced concrete culverts along the seaward side of the dam. The stone dam needs to ensure the safety and stability of water inflow.
取水池是一个长 110 米、宽 50 米的矩形池塘,池塘周围环绕着石坝。沿大坝向海一侧设置钢筋混凝土涵洞。石坝需要保证进水的安全稳定。

Design scheme for Outfall pipeline
排污管道设计方案

One ID 1200 GRP outfall pipeline are installed from the onshore outfall chamber to deep water in the sea. In order to protect the ioutfall pipeline from wave and current action, the pipelines are buried below original seabed surface, the top level of cover layer above the top of pipeline is controlled not to be higher than original seabed surface.
One ID 1200 GRP 排污管道 陆上排污口室安装到 深海中 以保护排污口管道免受波浪当前作,管道埋设在原始海床表面以下,控制管道顶部上方的覆盖层顶层不高于原始海床表面。

For offshore pipeline, once the foundation trench is excavated, crushed stone leveling layer will be placed at the bottom of trench, then the outfall pipe will be installed on it. Once pipe installation is done, crushed stone will be backfilled around the pipes with enough thickness. Finally, the upper part of the trench will be protected by armour rocks.
对于海上管道,一旦基坑开挖,碎石平整层将放置在沟槽底部 然后在其上安装排污 管道安装完成后,碎石将在管道周围回填足够厚度的管道。最后,战壕的上部将受到装甲石的保护

For onshore pipeline, except the backfill material will be replaced by excavation fills and no armour rocks, construction sequence is basically the same as offshore pipeline. The onshore trench should be backfilled to original ground level.
对于陆上管道, 除了回填材料将被填料取代没有装甲石外, 施工顺序海上管道基本相同 应回填至原始地面水平。

in . Once the foundation trench is excavated, crushed stone and armour rocks are placed around it. The thickness of cover layer should be no less than 2m.
在。一旦挖出地基沟,就会在其周围放置碎石和装甲石。覆盖层的厚度应不小于 2m。

Aids to Navigation
导航辅助设备

The aids to navigation will be floating aids for the Special mark for safe water. The design of the navigation aids will be in accordance with Zone A of the Maritime Buoyage System in the IALA recommendation and other related IALA recommendation.
导航辅助设备将是安全水域特殊标志的浮动辅助设备。助航设备的设计将符合 IALA 建议和其他相关 IALA 建议中海事浮标系统的 A 区。

New light buoys shall be installed to mark the location area of the water Intake channel and water outfall head.
安装新的照明浮标 以标示进水通道出水口头的位置区域

Each assembly of the floating aids will consist of one 2.4m diameter marine buoy, one LED marine lantern, one 12VDC battery and solar power generation system, and mooring hardware.
每个漂浮辅助设备组件将包括一个直径为 2.4 米的船用浮标、一个 LED 船用灯、 一个 12VDC 电池太阳能发电系统以及系泊硬件。

Detailed Engineering Plan
详细的工程计划

Contractor will provide a Detailed Engineering Plan showing all activities which shall explain the execution of the EPC stages
承包商将提供一份详细的工程计划,显示所有活动,其中应解释 EPC 阶段的执行情况

Collect Design Information Associated Site Visit
收集设计信息 相关的网站访问

The necessary data will be collected if the data shown in the tender Package and supplemented is not sufficient. And site visit is necessary at a proper time.
如果招标包中显示的数据不足并补充的数据不足,将收集必要的数据。在适当的时候进行实地考察是必要的

Numerical Model Studies
数值模型研究

Two model studies will be carried out:
将进行两项模型研究:

Numerical Wave Model Study
数值波模型研究

The main contents and requirements of this study are shown below: Wind velocity, Direction, Return period
本研究的主要内容和要求如下:风速、风向、重现期

Wave Maximum Height (Hmax), Wave Significant Height (Hs), Wave Period, Direction, Return Period.
波浪最大高度 (Hmax), 波浪有效高度 (Hs), 波浪周期, 方向, 返回周期。

If the wave data is obtained from a location at significant distance from the project site, suitable wave transformation study shall be performed to obtain the corrected wave parameters at the site location.
如果数据是从距离项目现场的位置获得的 则应进行适当的波变换研究以获得校正后的参数站点位置。

Numerical Current and Sediment Model Study
数值洋流和沉积物模型研究

The main contents and requirements of this study are shown below: Current Velocity, Direction, Return Period
本研究的主要内容和要求如下所示:当前速度、方向、返回周期

Erosion and Deposition, Coastal Evolution.
侵蚀和沉积,沿海演变。

Geotechnical investigation
岩土工程勘察

Geotechnical investigation
岩土工程勘察

The purpose of geotechnical investigation is to assess the geotechnical engineering condition and provide geotechnical engineering data for detailed design, the purpose of offshore geotechnical investigation include but not limited to the following:
岩土工程勘察的目的是评估岩土工程状况,为详细设计提供岩土工程数据,海洋岩土勘察的目的包括但不限于以下内容:

Investigate marine topography and geomorphology, geological conditions, geological disaster phenomenon, underwater obstacle, buried, hydrological and meteorological conditions along pipeline route;
调查管道沿线海洋地形地貌、地质条件、地质灾害现象、水下障碍物、埋藏、水文和气象条件;

Collect the data of investigation area including geography, regional geological, geotechnical engineering and hydrogeology etc.;
收集调查区域的数据,包括地理、区域地质、岩土工程和水文地质等;

Ascertain the origin, type, depth, distribution, engineering properties and the variation discipline of subsoil. Also provides the physical & mechanical properties indexes.
确定底土的来源、类型、深度、分布、工程特性和变化学科。还提供物理和机械性能指标。

Investigate the conditions of the underground water and sea water etc. Assess the corrosivity of rock-soil and water to material of construction and the metal;
调查地下水和海水等的条件。评估岩石-土壤和水对建筑材料和金属的腐蚀性 ;

Analyze and appraise the seismic effect of field, provide the seismic parameters, determine the possibility of the earthquake liquefaction.
分析和评估现场的地震效应,提供地震参数,确定地震液化的可能性。

The CUSTOMER is conducting a comprehensive sea area survey and will provide the initial results later
客户正在进行全面的海域调查,并将在稍后提供初步结果

Survey
调查

Contractor should perform some necessary survey works(if any), in accordance with the applicable Project specifications and the relevant regulations of the Saudi Arabia.
承包商根据适用的项目规范和沙特阿拉伯的相关规定 进行一些必要的测量工作 (如有 )。

The purpose of survey is to provide topographical data for design, topographical survey including but not limited to the following:
勘测的目的是为设计提供地形数据,地形勘测包括但不限于以下内容:

Survey is carried out along the survey area using single beam echo sounder, multi beam echo sounder or side scan sonar to obtain the seabed morphology, bathymetry, obstructions in the survey area.
使用单波束回声测深仪、多波束回声测深仪或侧扫声纳沿调查区域进行测量,以获取调查区域的海底形态、测深、障碍物

Detailed Design
详细设计

Contractor will review, amplify, correct, develop, and complete the detailed design. This development of the basic design for the marine facility shall be in sufficient detail to provide a design of the works that meet the requirements.
承包商将审查、放大、纠正、开发并完成详细设计。海洋设施基本设计的开发应足够详细,以提供满足要求的工程设计。

Contractor will prepare and issue all deliverables required to complete the design, including but not limited to:
承包商将准备并发布完成设计所需的所有可交付成果,包括但不限于:

Numerical current & sediment & wave study
数值电流 & 沉积物 & 波浪研究

Detailed design for pipeline
管道的详细设计

Detailed design for Marine structure
船用结构的详细设计

Detailed design for Navigation
导航的详细设计

Engineering Organization
工程组织

Engineering Location and Relationship
工程位置和关系

There shall be two engineering execution centers for the project. CONTRACOTR will set up home office in China, where will be the center for Engineering activities execution. CONTRACOTR will also set up Saudi Arabia Engineering Offices to support performance
该项目有两个工程执行中心 CONTRACOTR在中国设立总部,那里将成为工程活动执行的中心。CONTRACOTR 还将设立沙特阿拉伯工程办公室以支持性能

of the engineering activities. Main design will be performed in China.
的工程活动。主要设计将在中国进行。

However, to the convenient of site construction, the field engineering representatives will be designated to the site to support construction and ensure that materials and drawings are being delivered to site according to Project Schedule; moreover, they will act as the interface between site and the Engineering office, devoted to the solution of any engineering or interfacing problem which may arise at site throughout different work phases. Saudi Arabia office will be mainly used to ensure an enhanced rapid and efficient communication with OWNER, representatives of the OWNER and project site in Saudi Arabia.
但是,为了方便现场施工,将指定现场工程代表到现场支持施工,并确保材料和图纸按照项目进度运送到现场;此外,它们将充当现场和工程办公室之间的接口,致力于解决在不同工作阶段现场可能出现的任何工程或接口问题。沙特阿拉伯办事处将主要用于确保加强与 OWNER、OWNER 代表和沙特阿拉伯项目现场的快速和有效沟通。

An integrated engineering management team from CONTRACTOR will be established. All the engineering work will be managed, directed by engineering management team and engineering discipline leaders who will have the overall engineering management, administrative, approval and revision control responsibility from CONTRACTOR. All CONTRACTOR engineering offices follow the same Quality Management System, Procedures and work methods and every activity will be in accordance with the project quality plans, procedures, method statements approved by OWNER.
将建立 CONTRACTOR 的综合工程管理团队。所有工程工作都将由工程管理团队和工程学科负责人进行管理,他们将承担 CONTRACTOR 的整体工程管理、行政、批准和修订控制责任。所有承包商工程办公室都遵循相同的质量管理体系、程序和工作方法,每项活动都将按照业主批准的项目质量计划、程序、方法声明进行。

CONTRACTOR will form an integrated, multi-discipline engineering design team with well-balanced project experience, skills and qualifications to provide excellent engineering design service. Key engineering personnel will mobilize soon after Contract Effective Date to work.
CONTRACTOR 将组建一支综合的、多专业的工程设计团队,具有均衡的项目经验、技能和资格,以提供卓越的工程设计服务。关键工程人员将在合同生效日期后不久动员起来工作。

The engineering manager will move at the end of the engineering phase to the job site with the discipline field engineers to support Construction assistance to OWNER’s taking over in accordance with the Project requirements.
工程经理将在工程阶段结束时与学科现场工程师一起移动到工作现场 ,以支持根据项目要求OWNER 接管提供施工协助

Engineering Organization
工程组织

The design team will be comprehensive of all the Project Specialist Leaders involved so as to improve coordination and uniformity of design.
设计团队将由所有参与的项目专家负责人组成,以提高设计的协调性和统一性。

The organization of the Engineering Department is based on the following structure, which includes all involved Engineering disciplines. Discipline responsible person will under the Engineering Manager who will report to the Project Manager. The Project Specialist Leader(s) (PSL) will extract all relevant procedures from the Contract’s engineering standards, procedures, design practices and drafting manuals and copy all members of their respective design teams. All team members will review the relevant standards and procedures upon receipt and prior to starting any project work.
工程部门的组织基于以下结构,其中包括所有涉及的工程专业。专业负责人将在工程经理的领导下,工程经理将向项目经理汇报。项目专家负责人 (PSL) 将从合同的工程标准、程序、设计实践和起草手册中提取所有相关程序,并抄送他们各自设计团队的所有成员。所有团队成员在收到相关标准和程序后,在开始任何项目工作之前,都会进行审查。

Discipline involved in the Project will include followings:
本项目涉及的学科将包括以下内容:

Marine Structure
海洋结构

General Layout
总体布局

Aids to Navigation
导航辅助设备

Pipeline
管道

Hydrology
水文学

Bathymetric Survey & Geotechnical Investigation
测深和岩土工程调查

Organization Chart of Engineering Department sees below.
工程部的组织结构图见下文。

Figure 2.5.2-1 Engineering Organization Chart (Home office)
图 2.5.2-1 工程组织结构图(家庭办公室)

Responsibilities
责任

Engineering Manager
工程经理

The Engineering Manager shall be fully responsible for the work of the Engineering Department under the direct leadership of the Project Manager.
工程经理应在项目经理的直接领导下全面负责工程部的工作。

Accountabilities shall include, but not be limited to:
责任应包括但不限于:

Ensure engineering and design is executed for a fit-for-purpose facility;
确保为适合用途的设施执行工程和设计 ;

Ensure Change Management is properly implemented;
确保正确实施变更管理 ;

Conduct Peer Reviews to ensure technical integrity of the project;
进行同行评审以确保项目的技术完整性 ;

Ensure quality of the engineering work is maintained;
确保工程工作的质量得到维护;

Assist project management in controlling and monitoring engineering performance against budget and schedule;
协助项目管理根据预算和进度控制和监控工程绩效;

Ensure the individual and collective engineering team technical competency/skills are appropriate;
确保个人和集体工程团队的技术能力/技能是适当的;

Ensure technical data is managed as per PROJECT requirements;
确保按照 PROJECT 要求管理技术数据 ;

Confidentiality and Intellectual Property;
保密和知识产权 ;

Ensure the integrity and confidentiality of all intellectual property under agreed terms in the CONTRACT;
根据合同中约定的条款确保所有知识产权的完整性和机密性;

Coordinate with OWNER’s Engineering Manager.
与 OWNER 的工程经理协调。

Saudi Arabia office
沙特阿拉伯办事处

Engineering Department will, in accordance with the needs of SITE activities and construction schedule, mobilize each discipline's engineer to SITE in Saudi Arabia for construction support.
工程部将根据 SITE 活动的需要和施工进度,调动各专业的工程师到沙特阿拉伯的 SITE 进行施工支持。

Present the personnel requirements according to SITE construction schedule;
根据 SITE 施工进度提出人员需求 ;

Help to solve SITE technical problems;
帮助解决 SITE 技术问题;

Contact and report to Engineering Manager;
联系并向工程经理汇报 ;

Arrange and coordinate the work and accommodations of field staff of different disciplines.
安排和协调不同学科的现场工作人员的工作和住宿。

Lead Discipline Engineer (LDE)
首席学科工程师 (LDE)

The Lead Discipline Engineer shall be fully responsible for the work of:
首席学科工程师应全权负责以下工作:

Scheduling and estimating;
安排和估算;

Coordinate with OWNER’s discipline support at site;
在现场与 OWNER 的学科支持协调 ;

Take overall responsibilities for the integrity and quality of his own discipline's engineering and interface with other disciplines;
全面负责自己学科工程的完整性和质量,并与其他学科对接 ;

Establish technical measures and uniform technical requirements for his own discipline's engineering;
为本学科的工程制定技术措施和统一的技术要求;

Review & approve technical biding evaluation;
审查并批准技术投标评估;

Responsible for his own discipline's engineering preparation for commissioning;
负责本专业调试的工程准备工作;

Review & approve vendor data to suit project requirements;
审查并批准供应商数据以适应项目要求;

Organize the technical hand-over to VENDOR and OWNER; and
组织向 VENDOR 和 OWNER 的技术移交;

Participated in the construction review of VENDOR;
参与 VENDOR 的施工审查 ;

Review and Approval of vendor drawings and documents;
审查和批准供应商图纸和文件;

Production of engineering and design deliverables thorough nominated team.
制作工程和设计可交付成果 彻底提名团队。

Discipline Specialist
学科专家

Engineering department will assign at least three specialists for each discipline. The specialist shall be fully responsible for:
工程部门将为每个学科分配至少三名专家。专家应全权负责:

Discipline engineering technical key points and technical difficulties;
学科方向: 工程技术要点和技术难点;

Improvement and optimization of technical solution for relevant discipline;
相关学科技术方案的改进和优化 ;

Discipline engineering technical review;
学科工程技术评审;

Assist the Lead Discipline Engineer in doing review and approve technical biding evaluation; and
协助学科主编工程师进行技术投标评审和批准;

Assist the Lead Discipline Engineer in controlling the integrity and quality of his own discipline's engineering.
协助首席学科工程师控制其学科工程的完整性和质量。

Topographic Engineer
地形工程师

Is responsible for his own discipline’s work and submit topographic documents; and
负责本专业的工作,提交地形文件;

Contact and report to Engineering Manager for work progress.
联系并向工程经理报告工作进度。

Geological Engineer
地质工程师

Is responsible for his own discipline’s work and submit geological documents;
负责本专业的工作,提交地质文献;

Contact and report to Engineering Manager for work progress; and
联系并向工程经理报告工作进度;

Is responsible for geological sub-Contractor management and document review.
负责地质分包商管理和文件审核。

Quality Controller Engineer
质量控制工程师

Performs routine reviews of Engineering Design output documents, which are considered as “Self-Quality Checks and squad check” of the Engineering Department;
对工程设计输出文件进行例行审查,这些文件被视为工程部的“自我质量检查和小队检查”;

Is responsible for organization, coordination and verification of implementation and execution of the quality system on behalf of the Engineering Manager;
代表工程经理负责组织、协调和验证质量体系的实施和执行 ;

Is responsible for the organization, coordination, revision, explanation, issuing and management of development of procedures and job instructions under the supervision of the QA/QC Department, and responsible for the distributed documents with effect;
在 QA/QC 部门的监督,负责程序工作指导书的组织 、协调、修订、解释、发布和管理 并对分发的有效文件负责 ;

Is responsible for quality control during entire engineering, and giving preliminary direction, interim examination and evaluation of final results;
负责整个工程的质量控制,并给出初步指导、中期检查和最终结果的评估 ;

Is responsible for quality analysis and collection, handling, transmitting and feedback of quality related information; and
负责质量分析及质量相关信息的收集、处理、传递和反馈;

Is responsible for quality audits to meet the requirements of ISO9000 certification.
负责质量审核,满足 ISO9000 认证要求。

Schedule Control Engineer
进度控制工程师

Bear the responsibilities for working out detailed design schedule in conformity with the requirements of Project Control Department;
负责按照项目控制部的要求制定详细的设计进度表 ;

Check, supervise and coordinate the implementation of the detailed design schedule;
检查、监督和协调详细设计计划的实施;

Be responsible for issuing weekly progress reports and monthly progress reports, and submit to Project Control Department on time; and
负责出具每周进度报告和每月进度报告, 并按时提交给项目控制部;

Make reasonable modification of the schedule in order to match the requirements of the PROJECT and submit implementation to Project Control Department in time after the approval of the Engineering Department.
为配合本项目的要求,对进度进行合理修改 ,经工程批准及时项目控制提交实施

Document Control Engineer
文档控制工程师

Setting up of document control procedures to be followed on the project
建立项目要遵循的文件控制程序

Locating and filing PROJECT deliverables;
查找和归档 PROJECT 可交付成果;

Maintaining records of deliverables;
维护可交付成果的记录 ;

Issuance of PROJECT deliverables;
发布 PROJECT 可交付成果;

Logging of PROJECT deliverables received to/from OWNER and distribution of documents as per project distribution matrix;
记录收到/从 OWNER 收到的 PROJECT 可交付成果,并根据项目分配矩阵分发文件;

Locating and filing PROJECT correspondences;
查找和归档 PROJECT 通信;

Maintaining records of PROJECT correspondences;
维护 PROJECT 通信记录 ;

Issuance of PROJECT correspondences;
发布 PROJECT 信函;

Logging of PROJECT correspondences received to/from OWNER.
记录与 OWNER 之间的 PROJECT 通信

Archival of project documentation at completion of project.
在项目完成时存档项目文件

Engineering Schedule Management
工程进度管理

The Engineering Schedule will be prepared by professional software; it will be used for creating plan and schedule project and resources, organizing project dates for quick status reports, comparing actual performance with original plans.
工程进度表将由专业软件编制;它将用于创建计划和进度项目和资源、组织项目日期以获得快速状态报告、将实际绩效与原始计划进行比较。

Work Breakdown Structure will be firstly set up to divide and control the whole project schedule. Milestone schedule will be secondly prepared to match the period requirement of whole project schedule. Detailed Engineering Activities Schedule will be developed based on the milestone schedule. Engineering schedule will be analyzed & compared with the actual progress weekly and updated monthly.
首先建立工作分解结构划分和控制整个项目进度。 其次 ,将准备里程碑时间表 以匹配整个项目时间表周期要求 。详细的工程活动时间表将根据里程碑时间表制定。 每周分析工程进度并与实际进度进行比较 ,并每月更新。

Engineering Quality Management
工程质量管理

Engineering Quality Management
工程质量管理

Engineering department has complete quality management system, reliable management method and effective implementation measures and can determine and provide various resources required for the project, including human resources, special skills, technical and financial resources, infrastructures and working environment, etc.
工程部拥有完整的质量管理体系、可靠的管理方法和有效的实施措施,能够确定和提供项目所需的各种资源,包括人力资源、专项技能、技术和财务资源、基础设施和工作环境等。

Engineering department will carefully carry out design planning, design input, design review, design confirmation, design demonstration, design output, design products, prevention and control of non-conforming products, personnel training, information transfer among disciplines, etc. Moreover, it will strictly implement the quality assurance system and management documents, reinforce the process control, effectively carry out monitoring, measuring, analysis and improvement, ensuring compliance of the design documents and achievement of the quality objectives of the project.
工程部将认真进行设计规划、设计输入、设计评审、设计确认、设计论证、设计输出、设计产品、 不合格 人员培训、 学科间信息传递等工作。严格执行质量保证体系和管理文件, 加强过程控制, 有效进行监控、 测量、 分析和改进,确保设计文件的合规性和项目质量目标的实现

Quality Objective and Requirements
质量目标和要求

To assure good design quality management of this project, engineering department has established the following quality objectives and requirements:
为了确保本项目的良好设计质量管理,工程部制定了以下质量目标和要求:

The design documents will comply with the international standards, national standards and the standards specified by OWNER.
设计文件将符合国际标准、国家标准和 OWNER 指定的标准。

The product qualification rate reaches to 100%.
产品合格率达到 100%。

Quality Management Organizational Structure
质量管理组织架构

Engineering Manager
工程经理

Be the person for contract execution and the prime responsible person for the project quality.
成为合同执行的人 成为项目质量的主要负责人

Be responsible for project management and assume responsibility for the project target specified in the contract.
负责项目管理工作,对合同规定的项目目标负责

Be responsible for planning, organization, leadership and control of project implementation and assume full responsibility for the project quality.
负责项目实施的规划、组织、领导和控制,并对项目质量负全部责任

Review and approve the project quality control procedure and ensure that all the design works proceed according to the quality control procedure.
审查和批准项目质量控制程序,并确保所有设计工作都按照质量控制程序进行

Be responsible for management, appraisal, assessment and reward/punishment of the personnel at various work posts.
负责各工作岗位人员的管理、考核、考核和奖惩工作。

Be responsible for organizing the preparation of project design summarization and organizing the preparation of materials requesting for excellent design.
负责组织编制项目设计总结,组织编写优秀设计申请材料

Quality Controller
质量控制员

Be responsible for preparing the quality management documents for project team.
负责编写项目组的质量管理文件

Be responsible for propagandizing the quality management documents to the members of the project team, and guide, supervise, and check the implementation of quality management documents in the project.
负责向项目组成员宣传质量管理文件,指导、监督、检查质量管理文件在项目中的执行情况。

Be responsible for interpreting and receiving the quality consultation and quality complaints from OWNER and relevant interests.
负责翻译和接收 OWNER 和相关利益方的质量咨询和质量投诉。

Investigate, analyze and dispose of the quality problems arising on the project and reflect the relevant information to the project manager for China section.
调查、分析和处理项目中出现的质量问题,并将相关信息反映给中国部分的项目经理。

Object quality, establish a pre-warning mechanism, establish risk-eliminating measures and make them public to the members of the project team.
对象质量,建立预警机制,建立风险消除措施,并向项目组成员公开

Designers
设计师

Carefully investigate research and collect the relevant design information according to the design plans and design specifications and carry out comparison between schemes and techno-economic analysis according to the requirements of the contract and bidding documents.
根据设计方案和设计规范, 认真调查研究收集相关设计资料 ,并根据合同招标文件的要求进行方案间的比较和技术经济分析

Design shall comply with the requirements in respect of production, operation, safety, maintenance, and manufacturing and construction installation.
设计应当符合生产、经营、安全、维护、制造和施工安装的要求

Carefully implement the relevant standards, codes and design regulations and correctly apply basic information and design data.
认真执行相关标准、规范和设计规定,正确应用基本信息和设计数据。

Carefully carry out self-check of design documents and proofreading before publishing and sign them.
认真进行设计文件的自检校对后,方可发表并签名

Carefully address the design problems arising during the project operation.
认真解决项目运行过程中出现的设计问题

Checkers
跳棋

Check the design documents under the leadership of the director of the discipline.
在学科主任的领导下检查设计文件

Research design scheme and design principle together with the designers.
与设计师一起研究设计方案和设计原则

Be responsible for general proofreading of drawings, tables and texts, mainly determining if the selection of scales and views is appropriate. The drawings layout is neat and clear. The projection is complete. The coordinates, elevations, dimensions, digits, symbols, legends and title blocks are complete and accurate. The texts are smooth, concise, exact, complete and free of error.
负责图纸、表格、文字的一般校对,主要确定比例尺、视图的选择是否合适。图纸布局整洁清晰。投影已完成。坐标、标高、尺寸、数字、 符号、 图例标题完整准确 文本流畅、简洁、准确、完整且没有错误。

Be responsible for proofreading of calculations to determine if the calculation conditions, calculation data, calculation formula are selected correctly and for proofreading of the whole process of calculation and the calculation results.
负责计算的校对,判断计算条件、计算数据、计算公式是否选择正确,并负责计算全过程和计算结果的校对

Be responsible for confirming if the contents of design documents are complete without any omission and if they comply with the relevant standards, codes and regulations.
负责确认设计文件内容是否完整无遗漏,是否符合相关标准、规范和规定。

Implement the detailed regulations on professional proofreading and carry out proofreading and signature according to the regulations of these detailed regulations.
执行专业校对细则,按照本细则的规定进行校对签字

For the problems identified during the proofreading, discuss with the designers to properly dispose of such problems.
对于校对过程中发现的问题,请与设计师讨论妥善处理此类问题。

Reviewers
评论家

Be responsible for review of the design documents of the discipline.
负责审查本学科的设计文件

Participate in the discussion and research of the design principle and main technical problems, guide and help the designers and proofreading persons to address the difficulties, and assume main responsibility for the correctness and rationality of the main technical issues and technical schemes.
参与设计原则和主要技术问题的讨论和研究,指导和帮助设计人员和校对人员解决难点,主要技术问题和技术方案的正确性、 合理性承担主要责任

Be responsible for reviewing the main contents of the documents to determine if the design input data, important calculation methods and calculation results are correct and reliable. If the design contents are complete without any omission. And if the finished
负责审核文件的主要内容,确定设计输入数据、重要计算方法和计算结果是否正确可靠。如果设计内容完整且无遗漏。如果

design products comply with the relevant standards, codes and engineering design regulations.
设计产品符合相关标准、规范和工程设计规定。

Implement the detailed regulations on professional review to carry out review and signature according to these detailed regulations.
执行专业审核细则,按照本细则开展审核和签字

Properly dispose of different opinions between the designers and proofreading persons.
妥善处理设计师和校对人员之间的不同意见。

Signature according to these detailed regulations.
根据这些详细规定签字

Properly dispose of different opinions between the designers and proofreading persons.
妥善处理设计师和校对人员之间的不同意见。

Approval Persons
审批人员

Be responsible for approval of the professional design documents.
负责专业设计文件的审批

Correctly judge the major problems of principle, such as technical advancement, safety and reliability and economic rationality of the design schemes and be responsible for technical approval of the review results of design documents.
正确判断设计方案的技术先进性、 安全性和可靠性、经济合理性等重大原则问题,并负责设计文件评审结果的技术批件

Participate in professional review of major design principles and design schemes.
参与主要设计原则和设计方案的专业评审

Analyze the technical differences among the design, proofreading and review, and make decision after discussing and researching these differences together with the relevant personnel and departments.
分析设计、校对和审核之间的技术差异,并与相关人员和部门讨论研究这些差异后做出决定

Review and determine if the design complies with the relevant national and industrial codes, standards, regulations and rules, and if the design complies with the OWNER' technical requirements, and be held responsible for the quality of reviewed design documents.
审查并确定设计是否符合相关的国家和行业规范、标准、法规和规章,以及设计是否符合 OWNER 的技术要求,并对审查后的设计文件的质量负责。

Implement the detailed regulations on professional review to carry out review and signature according to these detailed regulations.
执行专业审核细则,按照本细则开展审核和签字

Quality management process and Control Points
质量管理流程和控制

Engineering department implements a cycling work method "plan, implement, check and improve" for design quality management to continuously improve the quality of design process and ensure that the delivered design products comply with the OWNER' requirements. The detailed quality management process is show as the figure below:
工程部对设计质量管理实行“计划、实施、检查和改进”的循环工作方法 持续改进设计过程的质量 ,确保交付的设计产品符合业主的要求。详细的质量管理流程如下图所示

Figure 2.7.4-1 Quality management process
图 2.7.4-1 质量管理流程

The key quality control points of design will be strictly managed and controlled to ensure that the quality of delivered design products complies with the required standards and the OWNER' relevant quality requirements and that the quality objective of the project is achieved.
设计的关键质量控制点进行严格管理和控制,以确保交付的设计产品的质量符合要求的标准业主的相关质量要求,并实现项目的质量目标

Design Changes
设计更改

Once the detail design document and drawings have been issued and approved by OWNER, CONTRACTOR will follow document and drawings mentioned above completely to execute the work.
一旦详细设计文件和图纸发布并得到业主的批准 ,承包商将完全按照上述文件和图纸执行工作。

All proposed changes from wherever they originate including CONTRACTOR, Vendors, sub- Contractor and OWNER shall be coordinated and recorded within a formal system. The changes shall be reviewed, verified and validated, as appropriate, and approved before implementation. The review of design changes shall not only include evaluation of the effect of the changes on constituent parts and product already delivered, but also include an assessment of the impact on cost, schedule, commercial, technical, quality, certification, construction, safety aspects and any other similar considerations, as appropriate, and the impact on the Contract. Records of the results of the review of changes and any necessary actions shall be maintained. Proposed changes shall be distributed to the affected departments, disciplines, organizations, and other affected groups, including construction when applicable for analysis prior to approval or rejection.
所有来自任何地方的拟议变更,包括承包商、供应商、分包商和业主,都应在正式系统内进行协调和记录。在实施之前,应酌情审查、验证和确认更改,并批准这些更改。对设计变更的审查不仅应包括对变更对组成部分和已交付产品的影响的评估,还应包括对成本、进度、商业、技术、质量、认证、施工、安全方面和任何其他类似考虑(视情况而定)的影响以及对合同的影响的评估。应保留更改审查结果和任何必要行动的记录。建议的更改应分发给受影响的部门、学科、组织和其他受影响的组,包括施工(如果适用),以便在批准或拒绝之前进行分析。

The CONTRACTOR Change Control System shall be interfaced with that of OWNER. A register, log, or index of approved and rejected changes shall be maintained. The process to run the Change Control System is described in below.
承包商变更控制系统应与业主的变更控制系统相连接。应维护已批准和已拒绝更改的注册、日志或索引。下面介绍了运行 Change Control System 的过程

Proposed of Design Changes
设计变更提案

Design changes can be proposed by OWNER or CONTRACTOR,
设计更改可以由 OWNER 或 CONTRACTOR 提出,

A written request for the design document changes must be prepared; form like Design Change Request (DCR), will be used.
必须准备一份关于外观设计文件变更的书面请求;将使用 Design Change Request (DCR) 等表单。

DCR describes the change and identifies the affected design documents. The DCR may be accompanied by sketches, drawings or calculations that clarify the design changes.
DCR 描述更改并识别受影响的设计文档。DCR 可能附有阐明设计更改的草图、图纸或计算。

Design changes proposed by CONTRACTOR
承包商提出的设计变更

CONTRACTOR proposed changes of design document. Engineering Manager will organize various levels personnel of the appropriate discipline to evaluate the design changes. The DCR accompanied with appropriate justification, including any sketches of proposed modifications, calculations or other supporting documentation should be prepared.
承包商提议对设计文件进行修改。工程经理将组织相应学科的各级人员对设计变更进行评估。应准备 DCR 并附有适当的理由,包括拟议修改、计算或其他支持文件的任何草图。

Design changes proposed by OWNER
OWNER 提出的设计更改

OWNER’s requests for design changes will be in writing, but may or may not include an explanation documents. After receipt OWNER’s requisition and within 7~10 days, CONTRACTOR shall prepare DCR, then notify OWNER to verify and validate.
业主的设计更改请求将以书面形式提出,但可能包括也可能不包括解释文件。在收到业主的申请后,承包商应在 7~10 天内准备 DCR,然后通知业主进行验证和确认。

Review of DCR
DCR 审查

DCR and its accompaniments should be reviewed and approved by Engineering Manager.
DCR 及其伴随物应由工程经理审查和批准。

Following reasons but not limited should be considered:
应考虑以下原因但不限于:

OWNER’s requirements with regards to overall design intent and philosophies, functionality, and adherence to specified codes and standards;
业主对整体设计意图和理念、功能以及遵守指定规范和标准的要求;

Impact on the construction, maintenance, operation, safety and integrity of the system; and Impact on the Project cost and schedule milestones
对系统的建设、维护、作、安全和完整性的影响;和对项目成本和进度里程碑的影响

After Engineering Manager’s approval, the DCR and its accompaniments should be submitted to OWNER for approval. If the design changes involved the Project cost and schedule milestones, the DCR and its accompaniments should also be reviewed and approved by Project Manager prior to OWNER.
在工程经理批准后, 应将 DCR 及其附件提交给 OWNER 进行批准。如果设计变更涉及项目成本和进度里程碑,则 DCR 及其伴随内容也应在 OWNER 之前由项目经理审查和批准

OWNER’s Approval of Design Changes
业主对设计变更的批准

OWNER shall, in writing, notify CONTRACTOR whether or not the DCR is approved. Approved design documents shall not be changed or modified unless the relative DCR and its accompaniments has been reviewed and approved completely by OWNER.
业主应以书面形式通知承包商 DCR 是否获得批准。除非相关 DCR 及其附件已完全由业主审查和批准,否则不得更改或修改批准的设计文件。

Revision of Affected Documents
受影响文件的修订

Once the DCR is approved by OWNER, urgent activities may proceed based on the modified/marked documents. The design changes shall be registered in the Registration Form
一旦 DCR 得到所有者的批准,紧急活动就可以根据修改/标记的文件进行。 设计变更应在注册表登记

of Change Notification by Quality control Engineer. Record of controlled documents shall be updated accordingly.
质量控制工程师的变更通知。受控文件的记录应相应更新。

In the meantime, CONTRACTOR shall expeditiously amend and issue the revised design documents. The changes in the design documents shall be clearly indicated and marked with a triangle “” with the revision number (for example “1” for Revision 1, etc.) indicated within the triangle. For drawings, the revision identification shall be clearly marked inside a circle or “cloud” around each change in the re-issued drawings. The marked and revised design documents shall be forwarded to the OWNER for further approval, after which the revised design documents will become the basis of the Project execution.
同时,承包商应迅速修改并发布修改后的设计文件。 设计文件中更改清楚地标明用三角形“ 标记 ,并在三角形内标明修订号(例如,“1”表示修订版 1 等 )。 对于图纸, 应在重新发布的图纸中每个更改的圆圈或“云”内清楚地标明修订标识“△”。标记和修改后的设计文件应转发给业主进一步批准,之后修改后的设计文件将成为项目执行的基础

Notification to Affected Parties
通知受影响

The Engineering Department shall list all parties affected by the DCN. The Document Control Engineer shall distribute copies of the approved DCN and all revised design documents to them.
工程列出DCN 影响的所有各方 文档控制工程师应将批准的 DCN 和所有修订后的设计文件的副本分发给他们。

Impact Due to Design Change Notice
设计变更通知的影响

All approved DCR and DCN shall be registered by the Engineering Department and shall be reported to other departments with the quantities of changes to the Project Cost and /or Project Execution Schedule.
所有批准的 DCR 和 DCN 应由工程部注册,并应其他部门报告项目成本和 /或项目执行进度的更改数量

Engineering Document Control
工程文档控制

Engineering deliverables list will be submitted to OWNER for approval upon Contract effective. The engineering deliverables will include the drawings, Detail Specifications, Data sheets, Reports and Procedures. Contractor will complete the detailed design according to the approved document list.
工程可交付成果清单将在合同生效提交给业主审批 。工程可交付成果将包括图纸、详细规格、数据表、报告和程序。承建商将根据批准的文件清单完成详细设计

Contractor will prepare Engineering deliverables submission procedure for approval and submit the deliverables as approved procedure.
承包商将准备工程可交付成果提交程序以供批准,并按批准的程序提交可交付成果。

Engineering department will establish a document control management system for full- process control on document preparation, review, approval, distribution, storage, use, modification, identification, recovery, and invalidation, to ensure all documents in use are valid and effective. Information exchange documents to the OWNER and relevant parties will be numbered according to the document numbering system. Such documents will be subject to the centralized control and management of the document control engineering, so as to ensure availability of effective documents and materials to the OWNER and project team members and project implementation in an orderly manner.
工程部将建立文件控制管理系统,对文件准备、审查、批准、分发、存储、使用、修改、 识别、 恢复失效进行全过程控制, 确保所有使用的文件有效且有效。向 OWNER 和相关方交换信息的文件将根据文件编号系统进行编号。此类文件将接受文件控制工程集中控制和管理 以确保 OWNER 和项目团队成员能够获得有效的文件和资料,并有序地实施项目。

Document management
文档管理

General requirements
一般要求

The engineering document control engineer shall register, distribute and properly keep the hard copies of all communication documents.
工程文档控制工程师应注册、分发并妥善保存所有通信文件的硬拷贝。

Soft copies of all documents received and sent shall be backed up at all times.
应始终备份所有接收和发送的文件的软拷贝。

The document control engineer shall manage all project output documents in a centralized manner.
文档控制工程师应集中管理所有项目输出文档。

All communication documents shall be kept in the designated place which shall be safe, fire-proof and confidential.
所有通信文件应保存在指定的地方,该地点应安全 、防火和保密。

Types of communication documents with relevant parties
与相关方的通信文件类型

With the OWNER Fax Correspondence
OWNER 传真通信

The OWNER’s engineering document circulation system Documents submitted for approval
业主的工程文件流通系统 提交审批的文件

Other types of documents
其他类型的文档

Communication documents within the OWNER and project team Memorandum
OWNER 和项目团队备忘录中的通信文档

Meeting minutes Emails
会议纪要 电子邮件

Project management information system Other types of documents
项目管理信息系统 其他类型文档

Communication documents with other parties Fax
与其他方的通信文件传真

Correspondence Emails
通信电子邮件

Other types of documents
其他类型的文档

Document numbering system
文档编号系统

After receipt of the letter of acceptance, engineering department will prepare project document and drawing numbering rules and formats according to the OWNER’s requirements, and submit the said rules and formats to the OWNER for review and approval within the specified time limit.
工程部收到验收函后,根据业主的要求准备项目文件和图纸编号规则和格式,并在规定的期限内将上述规则和格式提交业主审核批准。

Review and approval of design documents
审查和批准设计文件

Documents (drawings) of version 0.
版本 0 的文档(图纸)。

Duplicate and distribute documents (drawings) of version 0 to relevant departments.
将版本 0 的文档(图纸)复制并分发给相关部门。

Document publication and delivery
文档发布和交付

Document publication
文档发布

The document control engineer is in charge of document publication. The designers shall sign and file the documents according to engineering department’s file management regulations. The project manager shall determine the requirements for document publication, and the document control engineer shall fill in the document publication and binding application. The published documents shall be examined, identified, and registered by the document controller before distribution.
文档控制工程师负责文档发布。 设计人员按工程部档案管理规定签字并归档。项目经理确定文档发布要求,文档控制工程师填写文档发布和装订申请。在分发之前,文档控制者应检查、识别和注册已发布的文档

Document delivery
文档交付

The document controller shall fill in the document transmittal which shall be approved by the project manager, and pack the documents in a manner satisfying transportation requirements and with clear marks. Project documents shall be submitted via hand delivery or by mail.
文件控制员填写经项目经理批准的文件传送单 ,并按照满足运输要求的方式包装文件并带有清晰的标记。项目文件应通过专人递送或邮寄方式提交

For documents delivered by mail, the packing thereof shall at least contain the following information:
邮寄文件,其包装至少应包含下列资料:

Name and address of the receiving department. Name and contact information of the recipient. Whether acknowledgement of receipt is required.
接收部门的名称和地址。收件人的姓名和联系信息。是否需要确认收到。

Name, address and contact information of the sending unit.
发送单位的名称、地址和联系信息。

For documents submitted by hand delivery, the packing thereof shall specify the document name and the receiving unit.
专人投递的单证,其包装应注明单证名称和接收单位。

Document filing management
文档归档管理

After the assessment reports/special reports preliminarily designed and prepared by engineering department are replied to and approved, the document controller will collect, arrange and file the documents and materials.
工程初步设计编制的评估报告/专项报告得到答复批准后, 文件控制员对文件和资料进行收集、整理和归档

Confidentiality management
机密性管理

In order to strengthen and regulate management of confidential design project information and protect the legitimate rights and interests of the state, OWNER and project, we will strictly comply with the requirement of OWNER on Management of Confidential Information on Computers and Portable Storage Devices.
为加强和规范设计项目保密信息的管理,保护国家、业主和项目的合法权益,我们将严格遵守业主关于计算机和便携式存储设备保密信息管理的要求。

All materials, information and work achievements that are made available to the project department as a result of contract execution and performance with the OWNER are property of the OWNER, which the project department shall keep confidential. Without written consent of the OWNER, the design project department shall not disclose the said confidential information in any manner or use it for purposes irrelevant to the project during and after contract performance.
与业主签订和履行合同而提供给项目部门的所有材料、信息和工作成果均为业主的财产,项目部门应对其保密。未经业主书面同意 设计项目不得合同履行期间和合同履行后以任何方式披露上述保密信息或将其用于与项目无关的目的

Procurement Support
采购支持

Procurement phase is between engineering phase and construction phase and overlaps with them. In this phase Engineering Department will maintain personnel to make evaluation of vendors' technical proposal of equipment and material requisition. And related engineering
采购阶段介于工程阶段和施工阶段之间,并与它们重叠。在此阶段,工程部将派员对供应商的设备和技术提案和材料申请进行评估。及相关工程

deliverables will be updated in accordance with vendor's data after related vendors are decided, including update MR documents for order. The persons, who evaluate vendors' technical proposals, will be the original designers or reviewers to ensure design continuity.
在确定相关供应商后,将根据供应商的数据更新交付物,包括更新订单的 MR 文档。评估供应商技术提案的人员将是原始设计师或审阅者,以确保设计的连续性。

Procurement phase as downstream phase of engineering, so many interface exists between engineering and procurement. The procurement interface is listed hereafter:
采购阶段作为工程的下游阶段,工程和采购之间存在许多接口。采购界面如下:

To adjust engineering schedule as per procurement schedule especially procurement documents such as long lead items and others.
根据采购进度调整工程进度,尤其是采购文件,例如长交货期项目等

To prepare procurement documents such as technical specification, datasheets, material requisition (MR) and other support documents; to deliver these procurement documents to Procurement department for Inquiry;
准备采购文件,如技术规格、数据表、材料申请 (MR) 和其他支持文件;将这些采购文件交付采购部门进行查询;

To provide technical evaluation criteria for Inquiry;
询价提供技术评估标准 ;

To evaluate vendor’s technical proposals, to reply technical clarifications from vendors;
评估供应商的技术提案, 回复供应商的技术澄清 ;

To prepare technical evaluation bid (TBE);
准备技术评估标书 (TBE);

To keep updated technical documents to be informed to Procurement at the first moment;
保留最新的技术文件,以便在第一时间通知采购部;

To sign Technical Agreement with the final accepted Vendor with the lasted technical documents;
与最终接受的供应商签署技术协议以及最后的技术文件;

To review Vendor prints;
要查看供应商打印件;

To attend factory inspection, site inspection, if required.
如果需要,参加工厂检查、现场检查

To provide technical support for problem arising out of equipment / materials installation at site, if required.
如有需要,为现场设备/材料安装所出现的问题提供技术支持

Construction Support
施工支持

Engineering Department will assign engineers with full construction experience to provide support with respect to construction methods, procedures, and field installation alternatives, etc.
工程部将指派具有丰富施工经验的工程师,在施工方法、程序和现场安装方案等方面提供支持。

In construction phase, main engineering discipline engineers will be dispatched to the site to set up worksite engineering group for supporting construction progress. During the construction phase, the field engineers' main work is to resolve problems encountered in construction phase, optimize detailed design according to actual conditions. The field engineers will report functionally to the Project Engineer. There will be persons involved in the detail design work and for the major disciplines CONTRACTOR will dispatch engineering Lead Discipline Engineers to the site to ensure seamless transitioning from the project engineering organization to the worksite engineering organization.
在施工阶段,将派遣主要工程学科工程师到现场成立工地工程小组,以支持施工进度。在施工阶段,现场工程师的主要工作是解决施工阶段遇到的问题,根据实际情况优化详细设计。现场工程师项目工程师报告功能。人员参与详细设计工作 对于主要学科 ,承包商派遣工程主管学科工程师到现场,以确保从项目工程组织到工地工程组织的无缝过渡

The construction interface is listed hereafter:
构造界面如下:

To adjust engineering schedule as per construction schedule especially drawings related to construction;
根据施工进度调整工程进度,尤其是与施工相关的图纸 ;

To prepare technical documents and drawings, and provide detail requirement for installation and construction;
准备技术文件和图纸,并提供安装和施工的详细要求 ;

To share all the related technical documents and drawings to construction and improve technical documents and drawings as per their feedback;
所有相关的技术文件图纸共享给施工 并根据他们的反馈改进技术文件和图纸 ;

To jointly examine the technical documents and drawings with construction and deliver the design;
施工人员共同审查技术文件图纸交付设计;

To keep updated technical documents and drawings to be informed to construction at the first moment;
保持最新的技术文件和图纸,以便在第一时间通知施工人员;

To dispatch key discipline’s engineers to site for site service.
派遣关键学科的工程师到现场进行现场服务。

To provide technical support for all the problems raised in construction stage.
为施工阶段提出的所有问题提供技术支持

Procurement
采购

Objective
目的

The Objective of this chapter is to describe and outline the procurement activities to be undertaken by the CONTRACTOR during the execution of the Work.
本章的目的是描述和概述承包商在执行工作期间将进行的采购活动。

General
常规

The CONTRACTOR will be responsible for the procurement of all the plant, equipment, and materials, including the placement and management of its own construction equipment which applied for the execution of the work until final acceptance of all sections of the work.
承包商将负责采购所有厂房、设备和材料, 包括放置和管理其自己的建筑设备 ,这些设备申请执行工作,直到工作的所有部分最终验收

The CONTRACTOR will perform all the procurement activities including, but not limited to, purchasing, sub-contracting, expediting, inspection, quality assurance, storage, transportation, insurance, importation, customs clearance and related services required for the successful completion of the Work.
承包商将执行所有采购活动,包括但不限于采购、分包、催交、检查、质量保证、储存、运输、保险、进口、清关和成功完成工作所需的相关服务。

The CONTRACTOR and its subContractors will undertake and ensure that category items are sourced would meet the requirement of OWNER’s request.
承包商及其分包商承诺并确保采购的类别物品符合业主的要求。

The CONTRACTOR, when applicable, will source equipment, materials, and service from vendor's listed in OWNER’s vendor list as stipulated.
在适用的情况下,承包商将按照规定从业主供应商名单中列出的供应商处采购设备、材料和服务。

The CONTRACTOR and its subContractor will procure materials, equipment and services from OWNER nominated suppliers as identified in the agreement tender documents.
承包商及其分包商将向协议招标文件中确定的业主指定供应商采购材料、设备和服务。

The CONTRACTOR will ensure that all the spare parts, special tools and consumable items required for the work are identified and supplied in accordance with the quantities as stated in BOQ or contract agreement which will be supplied by the Contractor.
承包商将确保工作所需的所有备件、特殊工具和消耗品都已确定 ,并按照 BOQ 或合同协议中规定的数量供应 ,这些数量将由承包商提供。

Procurement organization
采购组织

The CONTRACTOR will establish its procurement organization to perform and organize the procurement activities during the execution of the Work. Procurement organization chart is shown as below:
承包商将建立其采购组织,以执行和组织工作执行期间的采购活动。采购组织结构图如下:

Figure 3.3-1 Procurement Organization Chart
图 3.3-1 采购组织结构图

Procurement plan
采购计划

Procurement idea and principle
采购思路及原则

Materials, equipment and services will be purchased and processed from vendors and suppliers in accordance with categories items, OWNER’s vendors list and selected nominated vendors
材料、设备和服务将根据类别项目、 所有者的供应商名单选定的指定供应商从供应商和供应商处购买和加工

Subject to the characteristics of the supply and demand of the engineering materials and equipment for the work, we classify the engineering materials into parts from local and foreign respectively. The procurement work will be arranged by procurement manager according to the procurement order of construction department. The procurement manager and procurement engineer will be responsible for the inquiry, negotiation and purchasing, selected agency for importation customs clearance and logistics.
根据工程材料和工作设备的供求特点 我们将工程材料分别分为本地国外的部分 采购工作将由采购经理根据 建设部的采购订单进行安排。采购经理和采购工程师负责询价、 洽谈采购, 选择代理进口清关和物流。

Procurement plan
采购计划

Main materials and equipment
主要材料及设备

Major materials and equipment form permanent project and facilities are shown below, which will be procure and supplied by the CONTRACTOR as required in the Time as scheduled.
永久性项目的主要材料和设备及设施如下,由承包人按要求按计划在时间内采购和供应。

Table 3.4.2-1 Main Materials and Equipment List
表 3.4.2-1 主要材料及设备清单

NO.

Materials
材料

Criticality Rating
关键性评级

1

GRP pipe
GRP 管材

Critical
危急

2

FittingElbow ReducerTeeFlangeDuckbill valveBolt and Nutsetc
配件 弯头 异径管 三通 法兰 鸭嘴阀 螺栓和螺母

Critical
危急

3

Aids to NavigationBuoyLight lanternSolar panelBattery and Battery boxetc
助航设备 浮标 灯笼 太阳能电池板 电池和电池盒

Normal
正常

General requirement
一般要求

The CONTRACTOR will develop a procurement schedule which include major items of materials, equipment and plant. Supplier/subContractor will be selected according to the scope of category/OWNER's vendor list. The procurement plan and associated procedures will incorporate all applicable requirements of the tender documents.
承包商将制定采购计划,其中包括材料、设备和工厂等主要项目。供应商/分包商将根据类别/业主的供应商列表的范围进行选择。采购计划和相关程序将纳入招标文件的所有适用要求。

Coordination and interface procedures between procurement manager and the OWNER. In order to have uniform tracking, control and reporting systems for information coming from suppliers.
采购经理 OWNER 之间的协调接口程序 。为了对来自供应商的信息建立统一的跟踪、控制和报告系统。

Definition of procurement strategy, taking into consideration specific requirement and objective.
定义采购策略,同时考虑具体要求和目标。

Procurement schedule in accordance with the work progress and requirements by construction department.
根据施工部门的工作进度和要求制定采购时间表

Criticality rating of equipment and materials based on design specification and the OWNER's requirement as stated in tender documents.
根据招标文件中规定的设计规范和业主的要求对设备和材料进行临界评级

Mandatory requirements (if any) for proposal items.
提案项目的强制性要求(如果有)。

Identification of all mandatory requirement imposed by applicable codes and standards, permits and laws for purchase orders.
确定适用规范标准、许可证和采购订单法律施加的所有强制性要求

Invitation to Bid and bid
邀请投标和投标
evaluation.
评估。

Technical requirement for equipment and materials will be prepared for bid proposal so as to make sure bidders understand all the requirements for the product.
投标人将准备设备和材料的技术要求,以确保投标人了解产品的所有要求。

Preparation and placing of purchase orders.
准备和下达采购订单

Surplus material management.
剩余物料管理。

In consideration of damage and lose during transportation, handling, necessary surplus material will be considered.
考虑到运输、搬运过程中的损坏和丢失,将考虑必要的剩余材料。

Expediting
加快

Steps necessary to ensure timely issuance of technical requisitions will be emphasized and checked from time to time.
将不时强调和检查确保及时发布技术申请的必要步骤。

Engineering department will communicate with procurement department from time to time to make sure the procurement manager and its assistants understand all the requirements for any equipment and materials.
工程部将不时与采购部沟通,以确保采购经理及其助理了解任何设备和材料的所有要求。

Actions will be taken to ascertain that purchase order's terms and delivery dates are met by vendor's.
将采取措施确保供应商满足采购订单的条款和交货日期。

Procurement department will be responsible for record and follow up actions.
采购部门将负责记录和跟进行动。

Documentation review
文件审查

List of deliverable from vendor's submitted for information, review or approval will be in accordance with requirement.
供应商提交的可交付成果清单以供参考、审查或批准将符合要求。

Conditions for review or approval of such deliverables and requirement for vendor will be documented.
将记录此类可交付成果的审查或批准条件和对供应商的要求。

Inspection
检查

List of manufacturing deliverable from vendor requiring approval
需要批准的供应商提供的制造交付物清单

In-house, shop and worksite inspection procedures, including progress reporting List and conditions of use of qualified independent inspection agencies
内部、车间和工地检查程序,包括进度报告合格独立检验机构的清单和使用条件

Individual inspection plans for equipment and materials, which will identify Contractor witness and hold points and include the review of vendor's data book and manufacturing data report
设备和材料的单独检查计划,将确定承包商见证和保留点,并包括对供应商数据簿和制造数据报告的审查

Plan for inspections at vendor workshop, and at worksite or re-fabrication locations Shop release and preparation for shipment procedure
计划在供应商车间、工地或再制造地点进行检查车间放行和装运程序准备

Non-conformance management procedure
不合格项管理程序

Shipping, imports and customs formalities
运输、进口和海关手续

Condition of involvement of vendor’s specialists at worksite.
供应商专家在工作场所的参与条件

Spare parts and special tools.
备件和专用工具。

Preservation of installed and non-installed equipment and materials.
保存已安装和未安装的设备和材料。

Management of package Contractor procurement activities
管理包承包商采购活动

Selection of vendor’s for equipment and materials
设备和材料的供应商选择

In accordance with tender requirement, CONTRACTOR will select all vendors according to the following order of priority:
根据招标要求,承建商将按以下优先次序选择所有供应商:

Nominated vendor's as identified in tender documents (especially Main vendor).
招标文件中确定的指定供应商(尤其是主供应商)。

Vendor's for Category Items as stated in tender documents
招标文件中规定的类别项目的供应商

Other reputable, capable and experienced vendor's
其他信誉良好、有能力和经验丰富的供应商

In cases where no mandatory Vendor is imposed, the CONTRACTOR will develop a specific bidders list submit for OWNER's approval prior to select vendor.
在没有强制供应商的情况下,承包商将制定一份具体的投标人名单,在选择供应商之前提交供业主批准

For procurement of any equipment or material with a criticality rating of critical or normal, the bidders list will be submitted to OWNER for approval prior to issue of any ITB (or equivalent) to bidders.
对于采购任何临界等级为“严重”或“正常”的设备或材料,投标人名单将在向投标人发布任何 ITB(或同等产品)之前提交给 OWNER 批准。

For any of the required equipment or materials, no vendor pre-qualified by the OWNER can be identified, The CONTRACTOR will propose and pre-qualify additional vendor's and provide following evidence and supporting documents for approval:
对于任何必需的设备或材料,无法确定业主资格预审的供应商 承包商提议资格预审其他供应商 并提供以下证据和支持文件以供批准:

Capabilities to meet the specifications and applicable codes and standard;
满足规范和适用规范和标准的能力;

Evaluation of vendor’s quality system;
供应商质量体系评估 ;

Technical support and after sales services;
技术支持和售后服务 ;

Company profile, financial capability, track record including references;
公司简介、财务能力、业绩记录(包括参考资料);

Capabilities to meet the delivery time required.
满足所需交货时间的能力

Construction
建设

General
常规

The Contractor will have full responsibility for the execution of the work and services related to the construction of the Project by providing all construction management supervisions, technical supports, labors, transportation, tools, construction equipment, materials, consumables, construction services at worksite and any other items or services required for construction. The Contractor will place the highest importance on the Health, Safety and Environment (HSE).
承包人将全权负责与项目施工相关的工作和服务的执行,提供所有施工管理监督、技术支持、劳动力、运输、工具、施工设备、材料、消耗品、工地施工服务以及施工所需的任何其他项目或服务。承包商将高度重视健康、安全和环境 (HSE)。

Construction strategy
施工策略

The preparation for the construction will be concurrent with the survey and design activities upon receiving the award of the works. The management team will get to site as soon as possible to carry out all the preparation work such as temporary facilities construction, mobilization activities for large equipment.
施工准备工作将与获得工程奖励后的勘察和设计活动同时进行。管理团队将尽快到达现场,进行所有准备工作,例如临时设施建设、大型设备的动员活动。

We target to execute survey and design work within four months, and we target to execute the procurement work when parts of the design work have been completed.
我们的目标是4 个月内完成勘察和设计工作 我们的目标是在部分设计工作完成后进行采购工作

Considering the limited construction period, the construction of the water intake and outfall shall be carried out at the same time.
考虑到施工工期有限,取水口和出水口的施工应同时进行。

Construction execution plan
施工执行计划

The Contractor will execute the work and construction activities in compliance with requirement of contract. The work will be safe, reliable and suitable for their intended purpose in accordance with the contract. The construction scope of the work is as shown following:
承包商将按照合同要求执行工作和施工活动 根据合同, 工作将是安全、 可靠适合预期目的的。工程施工范围如下

Fabrication of Intake channel ,intake pond and outfall pipes
制造进水通道、进水池和出水

Dredging off shore / Excavation on shore
近海疏浚 / 岸上挖掘

Pipeline installation
管道安装

Backfilling
回填

Required testing
所需测试

The Contractor will, when carrying out the work, supervise all construction activities, ensure equipment and materials availability, perform all the QA/QC and HSE activities during construction, control, assess and monitor the progress of the work and report daily, weekly and monthly to OWNER.
承包商在进行工作时,将监督所有施工活动,确保设备和材料的可用性,在施工期间执行所有 QA/QC 和 HSE 活动,控制、评估和监控工作进度,并每天、每周和每月向业主报告。

The Contractor will mobilize at the early stage of the design process in order to organize construction activities in a systematic and sequential manner to ensure that the work is carried out safely in accordance with the contract. Construction management and supervision will be performed by its management team.
承包商将在设计过程的早期阶段动员起来,以系统和顺序的方式组织施工活动 以确保工作按照合同安全进行。施工管理和监督将由其管理团队进行。

The Contractor will plan, execute, monitor and control all construction activities in accordance with the approved construction schedule.
承包商将根据批准的施工时间表计划、 执行、 监督和控制所有施工活动

Construction supervision and management function to be performed includes but not limited to the following key functions for effective execution, monitoring and control:
施工监督管理职能所要履行的包括但不限于以下关键职能,以便有效执行、监督和控制:

Managing and reporting;
管理和报告;

Planning, scheduling, quantity surveying;
规划、调度、工料测量;

Construction supervision, discipline-wise;
施工监理, 学科;

QA/QC performance, discipline-wise;
QA/QC 绩效, 学科方面;

Logisticsforshipping,customclearances,inlandtransportation performance;
航运物流 清关 内陆运输绩效;

Warehouse and material control management;
仓库和物料控制管理;

Field engineering and procurement activities;
现场工程和采购活动;

Health, Safety and Environment (HSE) management;
健康、安全和环境 (HSE) 管理;

Personnel/administration/industrial relations;
人事/行政/劳资关系;

Quality measurement;
质量测量;

Finance and accounting;
财务和会计;

Security.
安全。

Project Schedule Narrative
项目进度叙述

The CUSTOMER estimate to issue NTP on 1st July, 2025. Considering the Investigation and Survey, Modeling Test, Pipeline production and Transportation, the first batch of GRP is expected to arrive on 1st November, 2025. And excavation and dredging activities will begin one month before GRP arrival based on site wave conditions.
客户预计将于 202 年 7 月 1 日发布 NTP 5 考虑到调查和调查、建模测试、管道生产和运输,第一批 GRP 预计将于 202 年 11 月 1 日到达 5。挖掘和疏浚活动将根据现场波浪条件在 GRP 到达前一个月开始。

The estimated construction period is 16 months. For the detailed schedule, please refer to “Appendix 2: Schedule for Water Intake and Outfall of GHAZLAN Expansion 1 IPP PROJECT”.
预计施工周期为 16 个月。 详细时间表请参阅《 附录 2: 加兹兰 1 号扩建 IPP 项目水口和出水口时间表 》。

The critical activities of water intake and outfall construction are geotechnical investigation, engineering of pipeline, procurement of GRP, mobilization for dredging equipment, trench excavation, pipeline installation, backfill activities etc.
取水和排水口建设的关键活动是岩土工程勘察、管道工程、GRP 采购、疏浚设备动员、沟渠开挖、管道安装、回填活动等。

Preparation and Arrangement
准备和安排

The Project Management team will be established to take charge of daily construction management as soon as the contract is awarded. A qualified project manager will be stationed on site together with site supervisors, surveyor, administrative staff, equipment, personnel, technician, warehouse man, etc. to assure immediate and professional services for the execution of the works.
合同授予,将成立项目管理团队负责日常施工管理 合格的项目经理将与现场主管、测量师、行政人员、设备、人员、技术人员、仓库管理员等一起驻扎在现场,以确保为工程的执行提供即时和专业的服务

The construction program will be prepared with project software and then submitted by the Contractor to the Engineer for approval at the beginning stage of the contract. QC Plan and
施工计划将使用项目软件准备,然后由承包商在合同开始时提交给工程师批准。QC 计划和

Health, Safety & Environment Management Plan will be also be prepared and submitted to the Engineer. Once the program is approved, the project team will exercise their best effort to complement it.
健康、安全和环境管理计划也将准备并提交给工程师。 一旦该计划获得批准,项目团队将尽最大努力对其进行补充。

Document Preparation
文件准备

Before the construction commences, according to whole project construction schedule requirements, the shop drawings will be developed first according to the construction sequence. The method statement of dredging, GRP installation and other construction activities will be submitted to the Engineer to get approval before the associated work to be carried out.
施工开始前,根据整个项目施工进度要求,根据施工顺序先绘制施工图。疏浚、GRP 安装和其他施工活动的方法声明将提交给工程师,以便在进行相关工作之前获得批准。

Other construction associated documents will be submit to the Supervisor/Engineer as required.
其他施工相关文件将根据需要提交给主管/工程师。

Site Preparation
整地

At the time the project commences, Contractor will mobilize manual and material resources for the construction of access roads, materials storage area, cleaning and leveling the site.
在项目开始时,承包商将调动人工和材料资源来建设通道、材料储存区、清洁和平整现场。

The following factors are considered in selecting the project temporary construction site:
在选择项目临时施工地点时,考虑以下因素:

Meeting the requirements of local laws.
满足当地法律要求。

Meeting the requirements of construction specification.
满足施工规范的要求

The land shall be used economically and conveniently for construction.
该土地应经济、方便地用于建设。

The land shall be equipped with proper environmental protection and used in a civilization way.
土地应配备适当的环境保护,并以文明的方式使用

Reduce the influence caused by construction to the existing roads and nearby as far as possible.
尽可能减少施工对现有道路及附近地区的影响。

At the early stage of construction, Contractor would build temporary facilities like site office and workshop, etc. in the area designated by the OWNER. The temporary facilities include offices, storage yard of GRP and excavation material etc, temporary jetty and etc.
在施工初期,承包商将在业主指定的区域内建造临时设施,如工地办公室和车间等。临时设施包括办公室、GRP 和挖掘材料堆场等、临时码头等

The site offices will be set up near the construction site. Other facilities, such as the workshop, warehouse and material storage yard, will be arranged near the construction site.
工地办公室设立施工现场附近 其他设施,车间、仓库和材料储存场,将安排在施工现场附近

The area for the establishment of temporary facilities mentioned above shall be within 1km from the site or near the site and shall be provided by the OWNER for free.
上述临时设施的设立区域应在场地 1 公里范围内或场地附近,并由业主免费提供。

Pre-casting yard and temporary jetty to be built off shore with the distance of 400m, where the water depth is 2.5~3m. A temporary road will be the access to the temporary jetty.
预制堆场临时码头在离岸 400 米处, 水深为 2.5~3 米。临时道路将是通往临时码头的通道

Personnel Training
人才培养

The Contractor will give HSE induction training to all of its personnel prior to being permitted to work on site. Personnel identification badges will only be issued to those who have satisfactorily undergone the HSE induction. The mandatory HSE induction trainings for each individual working at the worksite will be carried out by HSE manager of the project management team and under the supervision of the OWNER. Except the HSE induction training, all personnel will be trained more as follows:
承包商在获准在现场工作之前,将对其所有人员进行 HSE 入职培训。人员识别徽章将仅颁发给那些满意地接受了 HSE 入职培训的人员。在工作场所工作的每个人的强制性 HSE 入职培训将由项目管理团队的 HSE 经理在业主的监督下进行。除 HSE 入职培训外,所有人员将接受以下培训:

Introduction of the contract works and construction meaning.
介绍承包工程和施工含义。

Introduction of profile and characteristics of the project, construction overall planning and precautions.
介绍项目的概况和特点、施工总体规划和注意事项。

Setting project goals, enhancing the project duration, quality and safety awareness;
设定项目目标,提高项目工期、质量和安全意识;

Stressing the specific requirements of high standard and efficient construction for this project.
强调本项目对高标准、高效施工的具体要求。

Mobilization of Staff
员工动员

On receipt of the notice of winning bid, Contractor will mobilize the first batch of management team to site. The technical personnel will be organized upon their arrival to be familiar with the design documents and prepare detailed plan for implementation of the construction. The bench mark and survey control points will be visited and readings checked. Other staffs will enter into site in batches according to the progress of the project.
在接中标通知 承建商动员第一批管理团队现场。 技术人员到达组织熟悉设计文件并准备实施施工的详细计划。将访问基准标记和测量控制点并检查读数。其他工作人员将根据项目进度分批进场

Mobilization of Machinery and Equipment
机械设备移动

Machinery and equipment shall be mobilized to the site in batches according to the construction schedule. The schedule may be adjusted according to actual site progress.
机械设备按施工进度分批调动到现场。时间表可能会根据实际现场进度进行调整。

The following ways will be used to mobilize the main equipment:
将使用以下方式来调动主要设备:

Rent local equipment
租用本地设备

It is our intention to rent some local equipment for temporary facilities at the beginning stage of the project. Additional equipment will be rent according to the construction schedule during construction stage.
我们打算在项目初期租用一些当地设备作为临时设施 施工阶段 将根据施工进度租用额外的设备

Mobilize equipment from abroad
国外调动设备

Some heavy and important equipment, such as flat barge, crawler crane etc. will be mobilized from China or other Country to site, since these equipments are owned by our Company.
一些重型重要的设备,平板驳船、 履带式起重机,将从中国或其他国家调动到现场,因为这些设备归本公司所有

Transportation management:
运输管理:

The Contractor will organize and coordinate the transportation of all equipment and material and maintain records of latest status. Prior to the transportation of any parts or components for the project, by sea, special means or any other mode of transportation. All the necessary permits should be obtained from marine or insurance surveyors or any other statutory body with respect to the means and procedure to be used during parking, weighting, loading, sea- fastening, transportation, off-loading etc.
承包商组织和协调所有设备和材料的运输 并保存最新状态的记录。在运输项目的任何零件或组件之前,通过海运、特殊方式或任何其他运输方式。在停泊、称重、装载、海上固定、运输、卸载等过程中使用的方法和程序,应从海事或保险验船师或任何其他法定机构获得所有必要的许可证

The Contractor will take the responsibility to make route survey for the transportation of any heavy and large equipment to worksite.
承包商负责任何重型和大型设备运输工作现场进行路线调查

The Contractor will ensure proper identification of all equipment and materials arrived at site at all phase of the project. All applicable certificates and documentation will be submitted to the OWNER upon delivery of such items at worksite.
承包商将确保在项目的所有阶段正确识别到达现场的所有设备和材料。所有适用的证书和文件将在工作场所交付此类物品时提交给所有者

Equipment and/or materials will be properly packed and secured so as to satisfactorily reach the worksite.
设备和 /或材料得到适当的包装固定 以便令人满意地到达工作现场。

The Contractor will undertake properly store and maintains any equipment or materials so as to protect them against weather, hazards, water, humidity, sand, fire, theft, vandalism and the like.
签约人应妥善保管和维护任何设备或材料,以保护它们免受天气、 危险、 水、湿气、 沙子、火灾、盗窃、故意破坏等的影响

During the transportation and storage period, the Contractor will take necessary measure to prevent any damage or loss whatsoever to equipment and materials.
在运输和保管期间,签约人应采取必要措施,以防止设备和材料发生任何损坏或损失

Materials Preparation
材料准备

Material testing
材料测试

According to the construction specifications and quality control system requirements, test the quality of materials and inspect strictly.
根据施工规范和质量控制体系要求,对材料质量进行检测并严格检验。

Material Storage
材料存储

A warehouse shall be built to store the main material and facilities, and a warehouse man will be responsible to guard the material.
应建造仓库来储存主要材料和设施,并由一名仓库管理员负责看守材料。

All circulating materials meet the site construction needs.
所有流通资料满足现场施工需要。

Storage Conditions
储存条件

Materials having special storage requirements will be kept in materials storage warehouse.
有特殊存储要求的材料将保存在材料存储仓库中。

The mainly construction method statement
主要施工方法陈述

The main construction procedure for water intake and outfall on shore/ off shore are shown as following flowchart:
岸上/离岸取水和排水口的主要施工流程 如下:

Figure 4.4-1 Flow chart of construction sequence for water intake and outfall on shore
图 4.4-1 岸上取水和排水口施工顺序流程图

Figure 4.4-2 Flow chart of construction sequence for water intake and outfall off shore
图 4.4-2 近海取水口和排水口施工顺序流程图

Trenching
挖沟

The setting out shall be done prior to excavation and dredging activities by surveying engineer.
测量工程师应在挖掘和疏浚活动之前完成放样。

Dewatering and Drainage shall be considered during excavation on shore. And sheet piles may be used as excavation supporting at the shore approaches based on site situation and slope stability calculation.
在岸上挖掘时应考虑排水和排水。根据现场情况和边坡稳定性计算,板桩可用作岸边通道的开挖支护。

Excavator and bulldozer will be used for land excavation. And the breaking hammer will be considered as deal with the hard bottom.
挖掘机和推土机将用于土地挖掘。而破锤将被视为处理硬底。

Grab Dredger will be used in this project for trenching off shore. In order to minimize the turbidity at sea, excavation materials shall be transferred to the dumping area that is allowed by the Authorities. Silt curtains will be used during the excavation.
Grab Dredger 将用于该项目的近海挖沟。为了尽量减少海上的浑浊度,挖掘材料应转移到当局允许的倾倒区。挖掘过程中将使用淤泥帘。

Bedding and Leveling
床上用品和调平

Bedding or levelling supports will create the conditions of lateral stability of the pipes during the haunching and backfilling.
垫层或调平支架将在腋下和回填过程中创造管道横向稳定性的条件。

Tolerances in the longitudinal and transverse profile of the bedding shall satisfy the requirement of the design specification.
垫层纵向和横向轮廓的公差应满足设计规范的要求。

Excavator will be used for bedding and leveling work on land. And the long arm excavator and divers will be used for bedding and leveling work underwater.
挖掘机用于陆地上的垫层和平工作 挖掘机和潜水员将用于水下垫料和调平工作

Pipe Installation
管道安装

Pipes will be stored on a flat surface and protected against mechanical damage which is near to the temporary Jetty in our project. The flat-bed cars will transfer the pipes to the location to be installed or temporary jetty. The pipeline shall be supported with saddles during transportation.
管道存放在平坦表面上 并防止我们项目中临时码头附近的机械损坏 。平板车将管道转移到需要安装的位置或临时码头。管道在运输过程中应由鞍座支撑。

Crawler crane will lift the pipe to install on land. The pipe can be jointed underwater with a hydraulic clamp or other specific equipment operated by manpower.
履带式起重机将提升管道以安装在陆地上。管道可以用液压夹或其他由人力作的特定设备在水下连接。

As for pipe installation under water, Crawler crane on flat barge will lift the pipe to install underwater. After the location confirmation of the installation barge, the preassembled sections or single pipes can be lowered to the bottom. The pipe can be jointed underwater with a hydraulic clamp or other specific equipment operated by divers.
至于水下管道安装 平板驳船上履带式起重机会将管道提升到水下安装。在确认安装驳船的位置后,可以将预组装的部分或单根管道下降到底部。管道可以用液压夹或潜水员作的其他特定设备在水下连接

During the installation, the weather conditions may change suddenly which will require the emergency protection of the pipes. Jumbo bag filling with gravels will be used as temporary protection for pipes.
在安装过程中,天气条件可能会突然变化,这将需要对管道进行紧急保护。装满砾石的大袋将用作管道的临时保护。

Backfilling
回填

The long arm excavator will used for backfilling surrounding the pipes which shall be more careful not to damage the pipes.
长臂挖掘机将用于管道周围的回填,应更加小心不要损坏管道。

Prefabrication and Installation for Water Intake Culvert
取水暗渠的预制及安装

All concrete of the project will be purchased from commercial concrete batching plant, which prior get approval by the inspector.
该项目的所有混凝土将从商业混凝土搅拌站购买,该厂事先获得检查员的批准。

Formwork, support, steel bar and embedded parts shall be re-checked before concrete is poured into formwork.
在将混凝土倒入模板之前,应重新检查模板、支架、钢筋和预埋件。

Concrete shall be cured by use of plastic membrane and spraying water with curing period of 7 or more days, water should be sprayed for enough times every day to keep the concrete wet.
混凝土应使用塑料膜和喷水固化,养护期为 7 天或以上,每天喷水应足够次数以保持混凝土湿润。

Once prefabrication completed and concrete strength satisfy the requirement for lifting, the floating crane will transfer and lift the riser to the location. The bedding & leveling and backfilling can refer to the above method mentioned.
一旦预制完成并且混凝土强度满足起吊要求,浮式起重机就会将立管转移并提升到该位置。床上用品和调平和回填可以参考上述方法。

Navigation facilities
导航设施

Navigation facilities include buoy lantern, solar power supply, power box. All the installation work will be carried out under the instruction of the engineer, the details shall satisfy with the technical specification.
导航设施包括浮标灯、太阳能电源、电源箱。所有安装工作将在工程师的指导下进行,细节应符合技术规范。

Health, Safety, Security and Environment plan for worksite
工作场所的健康、安全、安保和环境计划

Purpose
目的

The purpose of Health, Safety, Security and Environment plan for worksite is to outline the objectives to promote responsible safe and healthy working conduct for protecting the people who involve in the project, community and environment for all project operations and activities. Details objectives are as following:
工作场所健康 安全、 安保和环境计划的目的是概述促进负责任 、安全和健康的工作行为的目标, 以保护参与项目的人员 社区所有人的环境项目运营和活动。详细目标如下

As a management system to create and provide a safe and healthy environment for all conduct of personnel and operations for the project
作为为项目的所有人员和作创造和提供安全健康环境的管理系统

To generate and inform project management team and worker on leadership and senior management commitment toward managing and complying to HSE in project
生成并告知项目管理团队和工作人员对管理和遵守项目中 HSE 的领导力和高级管理层承诺

To provide organizational setup, resources and define responsibilities for managing HSE in project
提供组织设置、资源并定义管理项目中 HSE 的职责

To ensure HSE activities are planned
确保 HSE 活动得到规划

To implement planned HSE systems, procedure and activities in order to provide safe systems of work
实施有计划的 HSE 系统、程序和活动,以提供安全的工作系统

To monitor and measure HSE performance to ensure compliance and for improvement
监控和衡量 HSE 绩效,以确保合规性和改进

To ensure the preservation and protection of the natural environment
确保自然环境的保存和保护

To ensure the protection of the general public and surrounding community
确保公众周围社区保护

Scope
范围

This plan is intended to apply to all project activities carried out through this package. All conducts, operation and activities of The Contractor’s employee, subcontractors and third parties will comply to the requirement setting out in this HSE plan details referring to the HSE plan.
该计划适用于通过此包进行的所有项目活动。承包商的员工、分包商和第三方的所有行为、作和活动都将遵守HSE 计划细节中规定的要求 HSE 计划。

HSE Policy and Philosophy
HSE 政策和理念

The Contractor’s policy on HSE is going to provide the overall guideline and sets basic principle relating to HSE for daily HSE management, which are to be managed and integrated with overall business process throughout the project implementation and delivery processes in compliance with applicable local health, safety and environmental laws and regulations.
承包商的 HSE 政策将为日常 HSE 管理提供总体指导方针并设定HSE 相关的基本原则 这些原则在整个项目实施和交付过程中进行管理并与整个业务流程相结合,以遵守适用的当地健康、安全和环境法律。 法规。

Goals of HSE
HSE 的目标

The Goals set by the Contractor are as following
签约人设定的目标如下

To ensure compliance to regulation and full implementation of HSE actions as stated in HSE program
确保遵守法规全面实施 HSE 计划中规定的 HSE 行动

No harm to people, no accident, no damage to the environment & no loss of project’s property
对人无伤害 事故,环境破坏 &造成项目财产损失

Aim at zero fatality
以零死亡为目标

Aim at zero lost time injury days
以零损失工时工伤天数为目标

Minimize impact to natural environment in executing the construction works
在执行施工工程时尽量减少对自然环境的影响

For any details HSE plan and other management relating to HSE, please refer to HSE plan.
有关 HSE 计划和其他与 HSE 相关的管理细节,请参阅 HSE 计划。

Quality control
质量控制

General
常规

The purpose of the quality control is to ensure the constructed project is in full compliance with the project specification and the contract and the requirements of ISO 9001. Under such aspiration, the Contractor will assign a QA/QC manager and a group within its field organization that will have the responsibility to enforce the site quality requirements. The manager will be familiar with applicable law, international codes and standards,
质量控制的目的是确保所建造的项目完全符合项目规范和合同以及 ISO 9001 的要求。根据这一愿望,承包商将指派一名 QA/QC 经理和其现场组织内的一个小组,负责执行现场质量要求。经理将熟悉适用法律 国际规范和标准,

The Contractor will implement a comprehensive program of internal quality audits of its activities to be developed at worksite and activities executed outside of the worksite such as prefabrication, diving work, lifting work.
承包商将实施一项全面的内部质量审计计划,对在工地开展的活动和在工地外进行的活动(如预制、潜水工作、起重工作)进行内部质量审计。

The Contractor will strictly carry out quality control program during the performance of the work to ensure that the work is being executed in compliance with the project specification and the contract.
承包商工作执行期间严格执行质量控制计划 ,以确保工作按照项目规范和合同进行。

The Contractor will prepare a comprehensive set of inspection and test plans (ITP) for all disciplines or trades covering various construction phases of the work up to provisional acceptance. The Contractor will prepare and complete the construction check-sheets for each discipline. These documents will be incorporated into the respective system hand-over file.
承包商将为所有学科或行业准备一套全面的检验和测试计划 (ITP),涵盖工作的各个施工阶段,直到临时验收。 承包商准备完成每个专业的施工检查表 。这些文件将被纳入相应的系统移交文件中。

Site inspection and testing
现场检查和测试

The Contractor will organize and proceed with all necessary site inspections and tests in accordance with requirements of specification, codes and standards.
承包商将根据规范、规范和标准的要求组织并进行所有必要的现场检查和测试。

The Contractor will submit to the OWNER of its field quality control plan for approval, which details the hold points, witness points and surveillance activities.
承包商将向业主提交其现场质量控制计划以供批准,该计划详细说明了保留点、证人点和监督活动。

The Contractor will make sure that all materials stored have the identification stipulated in their respective specifications, and provide the necessary testing, measuring and calibration facilities and tools.
承包商确保储存的所有材料都符合其各自规格中规定的标识,并提供必要的测试、测量和校准设施和工具。

Pre-commissioning
预调试

Objective of Pre-commissioning
预调试目标

Since Pre-commissioning is the last phase leading to Mechanical completion, The Contractor will pay great attention into the preparation and execution of the pre-commissioning for the project in order to find any errors (if any) or unsafety fact and remedy them so as to bring it in a safe, planned, controlled and timely manner to its stable production stage.
由于预调试是机械完成前的最后阶段,承包商将非常注意项目预调试的准备和执行,以发现任何错误(如有)或不安全事实并进行补救,从而以安全、有计划、可控和及时的方式将其带入稳定的生产阶段。

Details & procedure of Pre-commissioning
预调试的详细信息和程序

All intake and outfall will be cleaned before commissioning by divers with the specific equipment.
所有进水口和出水口将在潜水员使用特定设备进行调试前进行清洁。

Appendix
附录

Appendix 16: Current stage drawings
附录 16 当前舞台图纸