Recommended Coating System 配套工艺 |
序号 Serial number | 编号 serial number | 产品名称 Product Name | 施工遍数 Construction times | 施工方法 Construction method | 施工注意事项 Construction precautions |
1 | \ | \ | \ | 铲刀等工具清理 Cleaning tools such as shovels | 1、基层干净无油污,含水率<10%, PH<10, 强度高无空鼓 1. The base is clean and oil-free , with a moisture content of <10%, PH<10, high strength and no hollows |
| | | | | 基面吸水性大时,需做界面剂或湿润 When the base surface has high water absorption, an interface agent or moistening is required. |
2 | \ | 粗腻子P型 Coarse putty P type | 2 | 批涂 Batch coating | 1、两遍之间应充分干燥,调配好的腻子建议2H内使用完, 1. The putty should be fully dried between coats. It is recommended to use the prepared putty within 2 hours. |
| | | | | 2、不能一次性厚批,否则易开裂空鼓; 2. Do not apply thick batches at one time, otherwise it will easily crack and hollow; |
| | | | | 3、干燥后的腻子建议及时打磨并养护 3. It is recommended to polish and maintain the dried putty in time |
3 | | 细腻子P型 Delicate P type | 1 | 批涂 Batch coating | 1、调配好的腻子建议2H内使用完,未及时使用完的腻子结块后不建议与新的腻子混合 1. It is recommended to use up the prepared putty within 2 hours. It is not recommended to mix the putty that has not been used up in time with new putty after it clumps. |
| | | | | 2、不能一次性厚批,否则易开裂空鼓 2. Do not apply thick batches at one time, otherwise it is easy to crack and hollow. |
| | | | | 3、干燥后的腻子建议及时打磨并养护 3. It is recommended to polish and maintain the dried putty in time |
4 | EX-PR110 | 外墙水性白色封闭底漆 Water-based white sealing primer for exterior walls | 1 | 辊/喷涂 Roller/Spray | 1、调配后充分搅拌均匀;搅拌后的产品建议当天使用完 1. Stir thoroughly after mixing; it is recommended to use the stirred product on the same day. |
| | | | | 2、底漆主要是以封闭为主,所以施工后的底漆要求均匀,无漏涂 2. The primer is mainly for sealing, so the primer after construction is required to be uniform without missing any part. |
5 | EX-MC800 | 花岗岩涂料A色 Granite paint color A | 2 | 辊/喷涂 Roller/Spray | 1、调配后的产品充分搅拌均匀并静置5分钟左右 1. Stir the prepared product thoroughly and let it stand for about 5 minutes. |
| | | | | 2、施工中每遍之间必须充分干燥 2. The surface must be fully dried between each pass during construction. |
| | | | | 3、施工后的墙面效果要求颜色均匀、无发花、无流挂 3. The wall effect after construction requires uniform color, no blooming, and no sagging |
| | | | | 4、不同批次产品不能施工在同一墙面,避免色差 4. Products from different batches cannot be applied on the same wall to avoid color difference. |
6 | EX-TC820 | 花岗岩涂料B色 Granite paint color B | 2 | 喷涂 Spraying | 1、调配或使用前,应倒桶混匀,切不可机械搅拌 1. Before mixing or using, pour the bucket and mix well. Do not stir mechanically. |
| | | | | 2、调试好喷枪后,第一遍满喷,干燥后喷涂第二遍 2. After debugging the spray gun, spray it fully for the first time, and spray it for the second time after it dries. |
| | | | | 3、第二遍根据样板彩点密度效果点喷,局部可以增加施工厚度 3. The second time, spray according to the density of the sample color dots, and the construction thickness can be increased locally. |
| | | | | 4、不同批次产品不用使用在同一墙面,避免出现色差 4. Products from different batches should not be used on the same wall to avoid color difference. |
| | | | | 5、是否加水及加水量根据使用习惯,可以不用加水直接使用 5. Whether to add water and the amount of water to add depends on usage habits. You can use it directly without adding water. |
7 | EX-TC900 | 水性丙烯酸哑光罩面漆 Water-based acrylic matte topcoat | 1 | 辊/喷涂 Roller/Spray | 1、调配后充分搅拌均匀 1. Stir well after mixing |
| | | | | 2、施工方式建议采用喷涂 2. Spraying is recommended as the construction method |
Application Precautions 施工注意事项 Application Precautions |
■施工前充分搅匀 ■ Stir thoroughly before construction ■均匀施工,防止局部过厚或漏涂 ■Uniform application to prevent partial over-thickness or missing coating ■保养时间(25℃/相对湿度75%):24h-48h,低温、高湿环境会适当延长 ■Maintenance time (25℃/relative humidity 75%): 24h-48h, the time will be extended appropriately in low temperature and high humidity environment ■勿在低温或潮湿的天气(气温低于8℃,相对湿度大于85%)施工,以免影响涂装效果 ■ Do not apply the paint in low temperature or humid weather (temperature below 8°C, relative humidity greater than 85%) to avoid affecting the painting effect. ■工具清洗:施工后立即用清水清洗。 ■ Tool cleaning: Clean with clean water immediately after construction. |
Safety Precautions 安全事项 |
■施工及待干过程中保持空气流通 ■Keep air circulating during construction and drying ■打磨墙面及涂装时应采取适当防护措施 ■ Take appropriate protective measures when sanding and painting walls ■在不良通风环境下施工,请配置适当呼吸设备 ■When working in a poorly ventilated environment, please use appropriate breathing equipment ■Further data please refer to the MSDS |
Storage & Transportation 存储和运输 |
■ Storage and transport must comply with national fire code requirements; ■ Store and transport at a temperature of not less than 0°C to prevent freezing; ■ Store in a cool and dry place; Keep out of reach of children |